TSK-000383 · Action
Scoped Full Removal and Replacement of 31,200 Sq ft Roof and 31,200 Sq ft Insulation
Warehouse Roof and Gutter Replacement
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-134 · Engineering case
Developed a phased warehouse roof and gutter replacement scope to protect inventory, operations, and building integrity.

Repair was no longer viable because multiple vendors identified severe age-related wear, deteriorated insulation, chronic gutter failures, unsafe walkability, and areas showing partial-collapse risk.
Scoped full removal and replacement of 31,200 sq ft roof and 31,200 sq ft insulation; PBR/RLOC Galvalume steel roof panels; Kynar 500 finish; 2-in vinyl-backed insulation; 1,000 LF gutters/downspouts; flashing/trim; product relocation; Side A/Side B sequencing; 12-ft maximum open roof sections; and 60-calendar-day phased execution while maintaining warehouse operation and inventory protection.
Developed a phased roof and gutter replacement scope, including inventory protection and live-warehouse sequencing.
Workstream Portfolio Rollup
5,695,000 USD
Environmental Compliance and Recovery Systems
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
Planned phased roof replacement to reduce water-intrusion and safety risks, protect stored materials, and maintain warehouse operation during execution.
Developed the warehouse building-envelope reliability scope, including 31,200 sq ft roof replacement, 1,000 LF gutters/downspouts, and 60-calendar-day phased execution, by sequencing section-by-section roof replacement while maintaining warehouse operations and inventory protection.
31,200 sq ft roof; 31,200 sq ft insulation; 1,000 LF gutters/downspouts; 60 calendar days; 12-ft maximum open section.
ACTIVITIES IN CONTEXT

TSK-000383 · Action
Warehouse Roof and Gutter Replacement

TSK-000384 · Technical scope
Warehouse Roof and Gutter Replacement

TSK-000385 · Technical scope
Warehouse Roof and Gutter Replacement

TSK-000386 · Technical scope
Warehouse Roof and Gutter Replacement

TSK-000387 · Technical scope
Warehouse Roof and Gutter Replacement

TSK-000388 · Technical scope
Warehouse Roof and Gutter Replacement

TSK-000389 · Action
Warehouse Roof and Gutter Replacement

TSK-000390 · Action
Warehouse Roof and Gutter Replacement

TSK-000391 · Action
Warehouse Roof and Gutter Replacement

TSK-000392 · Action
Warehouse Roof and Gutter Replacement

TSK-000393 · Method
Warehouse Roof and Gutter Replacement

TSK-001051 · Project communication
Warehouse Roof and Gutter Replacement
Full lifecycle project ownership
Direct Work
Developed the roof/gutter replacement scope, inventory-protection plan, staged-side execution constraints, schedule and risk presentation.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.