Food ingredients manufacturer Capital Project Engineer; owning workstream PG-B-05; authority Plant Manager.
2014-01-01 to 2016-09-30; budget $6,900,000; forecast variance (budget less EAC) $138,000.
Directed the translation of approved scope into procurement and supplier-data requirements, construction/configuration work packages, inspection and change records, mechanical completion and readiness evidence.
Used requirements-to-acceptance traceability, WBS and control schedule, cost/resource registers, agreements and acceptance records, baselines, risk/change controls, commissioning evidence, training, and G9 ownership transfer.
Cross-connection and backflow prevention; hygienic sampling; ozone/contact and filtration control; protected storage and distribution; hold-time control; chemical and microbiological qualification; quarantine and release before reuse; alarm and trend integrity; leak detection and process/utility separation.
76 controlled project documents across nine lifecycle phases, 362 linked execution records, accepted G1-G9 gates, and final baseline PRJ-B-006-BL-OT-B01.
OPERATIONAL / CLOSED; 1,200 lb/year biocide; 2,400 gal/year inhibitor; $82K/year energy/water savings; 300,000 gal/year reuse; operational turnover completed
Operations received Integrated sustainable utilities system with accepted configuration, procedures, training, asset and maintenance records, residual-item disposition, and ownership.
Delivered Integrated sustainable utilities system, measured by 1,200 lb/year biocide; 2,400 gal/year inhibitor; $82K/year energy/water savings; 300,000 gal/year reuse; operational turnover completed, by executing Rapid FEL / kaizen-capital hybrid from concept through G9 closeout.