Owned the full project lifecycle, from capital planning through commissioning and post-startup support. The acetator upgrades combined process support with practical maintenance access.
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-015 · Engineering case
Modernized acetator support equipment through mechanical, cooling, access and instrumentation improvements at the facility.

Upgraded acetator air and cooling support systems and improved maintainability of acetator support equipment through targeted mechanical and instrumentation upgrades.
Engineering scope: Acetator air screen and aspirator upgrades (75 hp), cooling system sump pumps, RTD temperature instrumentation, davit support installations.
Improved maintainability and reliability of acetator support equipment. The result is bounded to the recorded mechanical, cooling and instrumentation scope.
Workstream Portfolio Rollup
66,885,000 USD
Vinegar Acetation and Fermentation-Support Modernization
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
| Measure | Value | Type & meaning | Attribution & operating context |
|---|
Project scope and individual work packages are presented separately; project totals are not additive to their component values.
1 detail rows; 5,310 K project-family value.
ACTIVITIES IN CONTEXT

TSK-000021 · Technical context
Acetator Project A9 and A10

TSK-001037 · Design scope
Acetator Project A9 and A10
Full lifecycle project ownership
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Coordinated air-screen and 75 hp aspirator upgrades with sump pumps, RTD instrumentation and cooling requirements. The davit-support work made equipment access part of the engineering scope, linking process reliability with the way maintenance personnel would service the installation.