CASE-049 · Workstream overview

Chemical Dosing and Storage Modernization

An overview of the related projects, technical interfaces and outcomes within this workstream.

Conceptual engineering visualization: Production and Packaging Modernization
Conceptual engineering visualization · AI generated

Why the Work Mattered

Purpose and Operating Need

Project scope and individual work packages are presented separately; project totals are not additive to their component values.

Engineering Approach

Engineering Approach

Led engineering coordination for the combo-capper, conveyor, cryogenic dosing and bulk-nitrogen upgrades, including automated closure refilling, storage and cryogenic-piping interfaces, dosing verification, safety systems and SCADA telemetry. Developed AFE/budget scope and coordinated procurement, installation and startup.

Outcome & Engineering Context

Outcome and Context

The capital-planning workstream covers chemical dosing and storage modernization. Its portfolio value describes the represented project scope.

Workstream Results & Impact

Achieved 150 BPM rated capper capacity and improved nitrogen dosing verification at the SCADA layer.

Reduced changeover time by roughly 35 percent and improved cap application quality across multiple SKUs. Improved nitrogen-use efficiency by approximately 12 percent through bulk storage conversion and dosing optimization.

Reduced nitrogen loss by about 72 percent through bulk storage, cryogenic piping and dual-doser control integration. The documented nitrogen, vent-off and integration benefit is approximately $90,000 per year; these descriptions refer to one shared benefit.

Lowered unplanned downtime through conveyor-controls rework and coordinated closure handling, dosing verification and bulk-nitrogen supply.

Measures & Operating Detail

Engineering scope and design basis

Workstream covering chemical dosing and storage modernization across its named projects, with project-level engineering scope, capital values and operating context.

Delivered a combo capper rated at 150 BPM and improved nitrogen-dosing verification at the SCADA layer; The nitrogen business case modeled approximately $90K/year an annual benefit following coordination and tuning; Reduced changeover time by roughly 35 percent while improving cap application quality on multi-SKU runs; Improved nitrogen use efficiency by approximately 12 percent via bulk storage conversion and dosing optimization; Lowered unplanned downtime with conveyor-controls rework; the associated financial figure belongs to the same modeled benefit context; Reduced nitrogen loss by about 72 percent through bulk storage, cryogenic piping, and dual-doser control coordination; Evaluated nitrogen vent-off and inefficiency reduction within that modeled annual-benefit case.

Workstream Cost: 13500 K.

Coordinated the combo-capper, conveyor, closure-refill and cryogenic dosing upgrades with bulk-nitrogen storage, cryogenic piping, safety systems and SCADA dosing verification.

Bottling & Packaging Systems, Chemical Dosing & Metering, SCADA & Data Coordination; Chemical Dosing & Metering, SCADA & Data Coordination

Capital Project Lifecycle Management, QA/QC system implementation; AFE Development & Budget Modeling, Capital Project Lifecycle Management, Design-Build Project Coordination

Actions, Methods & Controls

ACTIVITIES IN CONTEXT

Additional Technical Detail

Roles & contributions
  • Project Ownership

    Full lifecycle project ownership

    Project Leadership

    Led engineering coordination and capital planning for capper, conveyor, cryogenic dosing, nitrogen storage, telemetry and SCADA interfaces.

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Workstream context
All portfolio connections
Related analysis and application artifacts

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗