Drumming Pasteurizer Analysis and Optimization Scope
Drumming pasteurizer analysis recording 190°F hot water, 89 GPM hot-water flow, 22 GPM vinegar flow, 136.9°F exit temperature, disabled regeneration, insulation and control limitations, 130-140°F fill target, 22-44 GPM target, and planned test work. Authority is observed and planned engineering evidence.