
TSK-000220 · Method
Coordinated the New 250-Ton Backup-Chiller Installation and Its Bulk Electrical Interfaces to Support the Expanded Cooling System
250-Ton Backup Chiller and 2000A 480V Bulk Electrical Upgrade
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-080 · Engineering case
Added dedicated backup cooling capacity and bulk electrical infrastructure to strengthen site utility resiliency.

Added dedicated backup cooling capacity and bulk electrical infrastructure to strengthen site utility resiliency.
Coordinated the new 250-ton backup-chiller installation and its bulk electrical interfaces to support the expanded cooling system.
Added dedicated backup cooling capacity and bulk electrical infrastructure to strengthen site utility resiliency.
Workstream Portfolio Rollup
14,998,000 USD
Cooling and Utility Reliability Modernization
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
| Measure | Value | Type & meaning | Attribution & operating context |
|---|---|---|---|
| Net Added Backup Cooling | 250 refrigeration tons | Equipment Rating Installed nominal cooling-capacity addition | Applies to: 250-Ton Backup Chiller and 2000A 480V Bulk Electrical Upgrade Net added backup cooling. |
| Bulk Service Current Rating | 2,000 A | Equipment Rating Electrical infrastructure rating | Applies to: 250-Ton Backup Chiller and 2000A 480V Bulk Electrical Upgrade 2000 amp, 480 V bulk electrical upgrade. |
Added +250 tons net backup capacity;2000 amp, 480 V bulk electrical upgrade.
ACTIVITIES IN CONTEXT

TSK-000220 · Method
250-Ton Backup Chiller and 2000A 480V Bulk Electrical Upgrade
Full lifecycle project ownership
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Project coordination
Project coordination
Mechanical and electrical installation responsibilities were assigned in the standby-chiller AFE.
Project coordination
Project coordination
Onsite startup by chiller manufacturer technicians was planned in the standby-chiller AFE.
Backup cooling electrical interface. The dedicated backup chiller and its 2000 A, 480 V support form a utility interface distinct from later site-service planning.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Coordinated removal and installation interfaces, piping connections, field work and startup readiness for the 250-ton chiller. The design and execution planning connected backup capacity with the plant's actual operating and maintenance needs.