TSK-001024 · Project design basis

Related the Acetator Expansion to the Existing Production Base, WDV Supply Deficit, Interplant Freight and Air-Emission Requirements for New and Existing Equipment

Explore the capability, case, and equipment connections for this activity.

Conceptual engineering illustration: fermentation process
Conceptual engineering visualization · AI generated

Case Context

Acetator Expansion ↗

Project Context

PRJ-A-009 · Acetator Expansion ↗

Capabilities

Measures & Operating Context

MeasureValueType & meaningAttribution & operating context
Existing Acetators7 unitsBaseline
Historical design basis

Applies to: Related the acetator expansion to the existing production base, WDV supply deficit, interplant freight and air-emission requirements for new and existing equipment

Pre-expansion — Existing acetators — Pre-expansion

Average WDV Production13,700,000 gal/yearBaseline
Historical design basis

Applies to: Related the acetator expansion to the existing production base, WDV supply deficit, interplant freight and air-emission requirements for new and existing equipment

Prior three-year average — Average WDV production — Prior three-year average

WDV Supply Shortage1,200,000 gal/yearEstimate
Forecast

Applies to: Related the acetator expansion to the existing production base, WDV supply deficit, interplant freight and air-emission requirements for new and existing equipment

2020 forecast — WDV supply shortage — 2020 forecast

New Scrubbers3 unitsScope or Inventory Quantity
Design scope

Applies to: Related the acetator expansion to the existing production base, WDV supply deficit, interplant freight and air-emission requirements for new and existing equipment

New and existing acetators — New scrubbers — New and existing acetators

Acetator Drive Power50 HPEquipment Rating
Design specification

Applies to: Related the acetator expansion to the existing production base, WDV supply deficit, interplant freight and air-emission requirements for new and existing equipment

Each new acetator — Acetator supplier drive power — Each new acetator

All Portfolio Connections

All portfolio connections (10)

Project Ownership and Delivery Context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Developed the integrated scope for acetator tanks, air and cooling services, scrubber connections, filtration and standby power. PLC and HMI requirements connected equipment behavior with operator visibility and the verification needed for startup.