Phased Electrical-Service and Feeder Scope
480V Phase 1 Electrical Service and Line 2 AFE Sequencing Strategy
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-101 · Workstream overview
An overview of the related projects, technical interfaces and outcomes within this workstream.

Project scope and individual work packages are presented separately; project totals are not additive to their component values.
Engineered phased 480/277V secondary service modernization designed for 2000A ultimate capacity. Defined Phase 1 installation of 1000A underground conduits and feeder conductors for new service, a NEMA 3R switchboard with SPD sized or expandable for a future 2000A upgrade, housekeeping pad, transformer pad and meter enclosure provisions, concrete sawcut and trench restoration, underground utility locates, and service grounding triad. Developed RFQ scope partitioning for secondary service and DP-PKG subpanel and feeder distribution. Aligned electrical utility pole placement and under-street bore timing with site enhancements to avoid future demolition through new concrete, curbing, and landscaping.
Developed underground-conduit and service-upgrade designs to support the 2040 demand forecast.
Prepared power distribution for growth through underground conduit banks, service modernization and long-range load planning aligned with 2040 demand forecasts.
Reduced outage exposure during expansion by separating critical loads and modernizing switchgear.
Defined utility rough-in, pole and under-street bore interfaces, feeder termination requirements, transformer and switchgear pad provisions, subpanels and distribution feeders as a coordinated installation sequence.
Developed and coordinated phased electrical-service modernization, RFQ/AFE scope, utility interfaces and future-capacity planning across the represented workstream.
Designed underground conduit banks and phased service upgrades to support 2040 demand forecasts; Planned critical-load separation and switchgear modernization to reduce outage risk during expansions; Defined baseline electrical utility rough-in scope for pole and under-street bore work, including utility guidance on feeder termination requirements; Established phased cost strategy for transformer and switchgear pad scope, with remaining switchgear, subpanels, and feeders staged for later execution.
Consolidated phased electrical-service engineering, capacity planning, RFQ/AFE scope, utility coordination, and future-expansion provisions within the project-family record.
Workstream Cost: 5555 K.
Capital Project Lifecycle and Multidisciplinary Coordination
ACTIVITIES IN CONTEXT

TSK-000246 · Technical context
Electrical Infrastructure Modernization Workstream

TSK-001072 · Design scope
Electrical Infrastructure Modernization Workstream
Full lifecycle project ownership
Direct Work
Developed phased 480/277V service design, RFQs, grounding/conduit/trench scope, electrical utility interfaces and capacity planning for future 2000A expansion.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
11 detail rows; 5,555 K project-family value.