Food ingredients manufacturer Capital Project Engineer; owning workstream PG-B-04; authority Plant Manager.
2012-06-01 to 2013-12-31; budget $2,600,000; forecast variance (budget less EAC) $52,000.
Directed the translation of approved scope into procurement and supplier-data requirements, construction/configuration work packages, inspection and change records, mechanical completion and readiness evidence.
Used requirements-to-acceptance traceability, WBS and control schedule, cost/resource registers, agreements and acceptance records, baselines, risk/change controls, commissioning evidence, training, and G9 ownership transfer.
Authoritative master data; route and priority rules; role-based schedule changes; versioned requirements; decision traceability; interface control; cybersecurity; sanitation windows; allergen or culture segregation; clean holds; QA release; human approval of schedules.
76 controlled project documents across nine lifecycle phases, 362 linked execution records, accepted G1-G9 gates, and final baseline PRJ-B-005-BL-OT-B01.
OPERATIONAL / CLOSED; 78 part variations; 20 processes; 3 customer types; operational turnover completed
Operations received MOM/MES scheduling solution with accepted configuration, procedures, training, asset and maintenance records, residual-item disposition, and ownership.
Delivered MOM/MES scheduling solution, measured by 78 part variations; 20 processes; 3 customer types; operational turnover completed, by executing Hybrid agile discovery plus stage-gate procurement from concept through G9 closeout.