A6-ACT-013 · Action
Coordinate Correction of Displayed Motor Amps Against the Panel Reading
A6 Acetator Workstream Updates and Inspection Protocol
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-036 · Engineering case
Defined controls, operator, maintenance, and vendor actions to improve A6 monitoring and inspection readiness.

The A6 issue exposed a monitoring gap: bearing temperatures and motor amps existed but were not configured correctly or captured for historical trending.
Coordinated the A6 monitoring updates: motor-amp alignment with panel readings, amps-versus-percent-FLA trending, correction of the erroneous 617 F display using the 150 F thermal imaging reference, the 230 F bearing alarm and airflow-trend repair. Defined the full-load airflow reference, +/-5 percent operator checks, bearing-grease PM review, and the drainage, rinsing, 24-hour ventilation and internal fiber-seal/air-piping inspection protocol.
Improved A6 monitoring, alarm response, PM quality, and inspection readiness.
Workstream Portfolio Rollup
66,885,000 USD
Vinegar Acetation and Fermentation-Support Modernization
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
| Measure | Value | Type & meaning | Attribution & operating context |
|---|---|---|---|
| Erroneous Bearing Display | 617 degF | Observation Invalid displayed value | Applies to: Specify correction of the erroneous bearing display using the thermal imaging reference A6 airflow and bearing-temperature investigation — Erroneous displayed value observed on the HMI; the independent thermal imaging bearing-temperature reference was 150 degF. |
| Bearing Temperature | 150 degF | Observation Validated reference | Applies to: Specify correction of the erroneous bearing display using the thermal imaging reference A6 airflow and bearing-temperature investigation |
| Bearing Alarm | 230 degF | Operating Control Recommended setting | Applies to: Specify the 230 F bearing-temperature alarm A6 recommended bearing alarm |
| Bearing Alarm | 230 degF | Operating Control Configured setting | Applies to: Specify the 230 F bearing-temperature alarm A6 recorded alarm configuration |
| Airflow Tolerance | -5 to 5 % | Operating Control Operating Control | Applies to: Specify operator airflow checks during charge and discharge Charge/discharge |
| Motor Loading | <= 80 % FLA | Operating Control Operator upper limit | Applies to: Define the steady-state motor-loading threshold for operator checks Steady state |
| Ventilation Duration | 24 h | Operating Control Inspection preparation condition | Applies to: Specify the 24-hour ventilation preparation period before internal inspection Before internal inspection — Recorded 24-hour ventilation preparation before internal inspection; retained as protocol/readiness rather than completed tank-entry evidence. |
| Startup Volume Context | 4,000 gal | Unresolved Value Open-question context | Applies to: Retain startup FLA question at 4000 gallons Startup — Unresolved question concerning startup motor loading at 4,000 gallons. |
Improved monitoring and trend visibility through coordinated controls updates; defined operator checks, PM review and internal-inspection preparation.
Defined the A6 monitoring and inspection protocol using a 230 F bearing alarm, <=80 percent FLA steady-state operator threshold, +/-5 percent airflow check and 24-hour tank-ventilation preparation, with separate controls, operator, maintenance and vendor actions.
230 F bearing alarm; <=80 percent FLA steady-state threshold; +/-5 percent airflow tolerance; 24-hour ventilation before entry; 4000-gallon startup FLA question to resolve.
Coordinated PLC/HMI monitoring updates and developed the operator checklist and PM review; specified tank-entry preparation, pre-kitted parts, fiber-seal inspection and acetator-coupling verification.
ACTIVITIES IN CONTEXT

A6-ACT-013 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-014 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-015 · Method
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-016 · Control
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-017 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-018 · Method
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-019 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-020 · Control
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-021 · Control
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-022 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-023 · Method
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-024 · Method
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-025 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-026 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-027 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-028 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-029 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-030 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-031 · Method
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-032 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-033 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-034 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-035 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-036 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-037 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-038 · Action
A6 Acetator Workstream Updates and Inspection Protocol

A6-ACT-039 · Question
A6 Acetator Workstream Updates and Inspection Protocol
Full lifecycle project ownership
Engineering Work and Coordination
Defined and coordinated the A6 monitoring, operator-check, PM and internal-inspection protocol, including motor-current/airflow trends, bearing alarm and tank-preparation requirements.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Project coordination
Project coordination
Controls, operators and maintenance were assigned monitoring changes, checks, PM and tank-preparation/inspection actions in the protocol.
Project coordination
Project coordination
Vendor inspection/check actions were included in the internal-aerator and coupling protocol.
The temperature comparison relates an invalid 617°F display to a 150°F thermal-imaging reference. The 4,000-gallon startup loading question remains unresolved.
Defined the A6 tank-preparation and internal-inspection protocol, including drainage, rinsing, ventilation, and component-inspection actions.