PARTICIPANT
Vendor and OEM Team
Follow the connected work in the portfolio.

Contributions Across the Portfolio
Vendor Startup and Training
Supplier Participation
Vendor Contribution
Provided startup and training support for the Line 1 filler-valve and product-return upgrade.
Coordinated Installation of the Filler-Valve/Manifold System, Return Tank and Pump, Relay Logic, Level Instrumentation, Sanitary Pump and Electrical Controls, with Vendor Startup and Training
Supplier Participation
Vendor Contribution
Supported startup and training for the installed Line 1 filler and product-return equipment.
Coordinated Installation of the Combo Capper, Conveyors, Cap Elevator, Cryogenic Dosing Retrofit, Bulk Storage, Telemetry, SCADA Controls and Safety Interlocks, with Vendor-Supported Startup
Supplier Participation
Vendor Contribution
Supported startup of the capper, conveyor and nitrogen-system upgrade.
Scope Development, Contractor and Vendor Coordination, Controls Coordination, Safety and Risk Reduction, Commissioning Planning
Supplier Participation
Project coordination
Vendor coordination was included in boiler and steam scope development and commissioning planning.
Led Supplier Evaluation and Trials, Comparing Legacy Centrifuge Performance with Alternative Centrifuge Suppliers
Supplier Participation
Supplier Reference
Supplier equipment and trial evidence were compared with legacy centrifuge supplier performance during centrifuge evaluation.
Centrifuge Skid, Membrane and Wastewater Interfaces
Supplier Participation
Project coordination
Vendor startup and operator training were included in the centrifuge execution plan.
Used Weighted Scoring, Compliance Indexes, Maturity Models, Field-Testing Criteria, Vendor Engagement, User Feedback, Documentation Review, and TCO Analysis
Supplier Participation
Supplier Reference
Supplier information and engagement informed the centrifuge evaluation, documentation review and lifecycle-cost comparison.
Researched More Than 40 Manufacturing-System Suppliers and Contacted More Than 15 While Evaluating the MOM/MES Solution
Supplier Participation
Supplier Reference
Manufacturing-system suppliers were researched and contacted during MOM/MES solution selection.
Centrifuge Piloting Compared the Brew 250 and Three Other Centrifuge-Supplier Alternatives Across Throughput, Solids Removal, Outlet Clarity, Automation, Documentation, Serviceability, Reliability, and Lifecycle Cost
Supplier Participation
Supplier Reference
Centrifuge supplier, centrifuge supplier, centrifuge supplier and an alternate supplier were included in the centrifuge comparison.
Coordinate Vendor Actions
Supplier Participation
Project coordination
Vendor follow-up was included in the A6 controls, operator and maintenance action plan.
Planned Temporary Tri-Clamp and Camlock Connections, Sanitary Sampling Valves, Hoses, Drain Routing, CIP Adaptation, Flow Measurement, HMI Access, Vendor Laboratory Support and ROI/TCO Evaluation
Supplier Participation
Project coordination
Vendor laboratory support and technician participation were planned for the temporary decanter trial.
Compared Supplier Documentation, Automation, Serviceability, Performance and Lifecycle Cost
Supplier Participation
Supplier Reference
Supplier documentation, automation, serviceability, performance and lifecycle cost informed the centrifuge comparison.
Coordinated Supplier Startup and Operating-Team Training
Supplier Participation
Project coordination
Centrifuge supplier startup and operator training were planned after the skid utilities were connected.
Developed Vendor and Execution Alternatives
Supplier Participation
Supplier Reference
Supplier alternatives were considered in winery-centrifuge option and execution planning.
The Tank-Level Measurement Record Identifies Preferred-Vendor and Purchasing Interfaces
Supplier Participation
Supplier Reference
Preferred instrumentation vendors were referenced in tank-level standardization planning.
The Tank-Measurement Scope Aligns Instrumentation Requirements with the Engineering Team's Preferred Vendor
Supplier Participation
Supplier Reference
The preferred instrumentation supplier instrumentation approach informed tank-measurement requirements.
Vendor Research, Configuration, Interfaces and Pilot Deployment
Supplier Participation
Supplier Reference
Vendor solutions were researched and selected as inputs to MOM/MES configuration and pilot deployment.
Centrifuge Supplier Evaluation and Manufacturing Maturity Scorecard
Supplier Evidence and Technical Reference
Supplier Reference
Centrifuge supplier, centrifuge supplier and other suppliers provided quotations, service terms, equipment documentation and technical responses for The comparison.
Centrifuge Trial Performance, Documentation, and Supplier Tradeoff Analysis
Supplier Participation
Vendor Contribution
Suppliers and site personnel generated trial observations and proposed equipment/control changes; supplier feasibility, final safety functions and later hardware changes were evaluated separately.
A6 Acetator Workstream Updates and Inspection Protocol
Project coordination
Project coordination
Vendor inspection/check actions were included in the internal-aerator and coupling protocol.
Centrifuge SPO, Supplier Evaluation, and Lessons-Learned Transfer
Supplier Evidence and Technical Reference
Supplier Reference
Centrifuge suppliers supplied service, controls, recalibration and feasibility responses; future control changes and machine retention remained decision items.
Winery Centrifuge and CIP Interface Engineering + Vinegar Transfer Centrifuge Loop
Supplier Participation
Vendor Contribution
Centrifuge supplier and centrifuge supplier supplied centrifuge trial and equipment evidence used in the integration decision; future PLC/HMI transfer integration required separate support.
Line 1 Capper, Conveyor, Cap Elevator, Cryogenic Dosing, and Bulk Nitrogen Modernization
Supplier Participation
Vendor Contribution
Vendor-supported startup was part of the capper, cryogenic dosing and nitrogen-system integration.
Line 1 Capper and Conveyor Upgrade + Bulk Nitrogen Transition
Supplier Participation
Vendor Contribution
Vendor-supported startup was part of the capper, cryogenic dosing and nitrogen-system integration.
Nitrogen Dosing, Automated Microbulk Refill Station + Storage Tank Conversion
Supplier Participation
Vendor Contribution
Vendor-supported startup was part of the capper, cryogenic dosing and nitrogen-system integration.
Centrifuge Installation and Interface Engineering
Supplier Participation
Vendor Contribution
Provided supplier startup and operator training for the centrifuge installation.