Added Financial/Risk Modeling Showing Approximately $1.80 OPEX Exposure for Every $1 in Chiller Repair Cost, Driven by Freight, Tanker Hauling, and Overtime from Forced Downtime

Explore the capability, case, and equipment connections for this activity.

Conceptual engineering illustration: risk reliability
Conceptual engineering visualization · AI generated

Case Context

Cooling Downtime-Cost and Repair-Risk Analysis ↗

Project Context

PRJ-A-021 · Production-Cooling Upgrade with Three 160-Ton Chillers ↗

Capabilities

Systems & Equipment

All Portfolio Connections

All portfolio connections (14)

Project Ownership and Delivery Context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

modeled demand and the roughly 78-ton peak thermal deficit, coordinated pumps and recirculation, and developed chiller staging and runtime balancing. Operating visibility and process-load monitoring connected the three 160-ton production chillers with the way the plant used cooling capacity.