PRJ-A-033 · Drainage and Erosion-Control Project Overview ↗Capabilities
- Specify Concrete Foundations and RestorationRecorded application
Why these connect
The source model links this activity to the capability.
All Portfolio Connections
All portfolio connections (5)
- Civil, Structural, Concrete, and Site Engineering — Application Review Review artifact
- Specify Concrete Foundations and Restoration Recorded application
- 12-in Steel Dowels Every 4 ft ↗ Existing portfolio connection
- Drainage and Erosion-Control Project Overview Existing portfolio connection
- Drainage, Weir, Debris Screen, Outlet Basin, and Phase 1 Remediation Existing portfolio connection
Project Ownership and Delivery Context
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Developed the reinforced channel, debris screens, five-step weir, outlet basin and stabilization scope. Curbing, grading, landscaping and wastewater-collection interfaces were coordinated with the work. The system reduced sediment carry by more than 90 percent while providing a maintainable runoff path.