Capital Strategy and Business Alignment
Translate Growth Forecasts, Customer Demand, Operating Constraints, and Asset Condition into Capital Priorities
Engineering practice and documented application
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPPRJ-B-008 · Food ingredients manufacturer
Owned the full project lifecycle, connecting capital planning, engineering, procurement, construction and operating readiness.

Workstream: Environmental Compliance and Recovery Systems
Refrigeration controls, instrumentation, piping, documents and commissioning preparation within the handed-off phases.
Refrigeration safety, documentation, relief protection, mechanical integrity, controls, MOC/PSSR, testing, training, and turnover.
Full lifecycle project ownership
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Project execution
Project Team Contribution

Capital Strategy and Business Alignment
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

TSK-000759 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000768 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

Action
Applies capabilities

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

Lifecycle Artifacts: Front-End and Design
Engineering practice and documented application

TSK-000760 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

TSK-000760 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000764 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

AFE and Capital-Governance Controls
Engineering practice and documented application

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

TSK-000764 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000768 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

TSK-000760 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000768 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Lifecycle Artifacts: Startup, Acceptance, and Closeout
Engineering practice and documented application

Lifecycle Artifacts: Startup, Acceptance, and Closeout
Engineering practice and documented application

Lifecycle Artifacts: Startup, Acceptance, and Closeout
Engineering practice and documented application

TSK-000764 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000768 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000776 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000778 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit
Owned capital planning and the full delivery lifecycle. The cards connect the applicable responsibilities with the recorded work.

Capital Strategy and Business Alignment
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

AFE and Capital-Governance Controls
Engineering practice and documented application

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application








Investment Economics and Lifecycle Analysis
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Optimization and Operations Research
Academic preparation and analytical method

Optimization and Operations Research
Engineering practice and documented application

Forecasting, Inventory, Supply Chain, and Logistics
Academic preparation and analytical method

Forecasting, Inventory, Supply Chain, and Logistics
Academic preparation and analytical method

Stochastic Models and Uncertainty Analytics
Academic preparation and analytical method

Stochastic Models and Uncertainty Analytics
Academic preparation and analytical method

Stochastic Models and Uncertainty Analytics
Academic preparation and analytical method

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Lean Six Sigma, Quality Systems, and Governance Maturity
Engineering practice and documented application

Investment Economics and Lifecycle Analysis
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Optimization and Operations Research
Academic preparation and analytical method

Optimization and Operations Research
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Ventilation, Control Rooms, and Equipment Protection
Engineering practice and documented application

TSK-000954 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit
Recorded applicationAmmonia/glycol safety, documentation, IIAR 9, relief protection, mechanical integrity, controls, MOC/PSSR, testing, training, and turnover; Budget: $900,000. Refrigeration system operationally transferred and closed; Owned the full project lifecycle.
Delivered refrigeration scope included P&ID recovery, field walkdown, charge calculation, IIAR 9 evaluation, machinery-room life safety, relief validation, mechanical-integrity restoration, glycol review, controls and interlocks, PM alignment, MOC/PSSR, testing, training, as-builts, startup, and turnover; Ammonia/glycol refrigeration system; 648 lb NH3 reduction; 250 P&ID items; 40 relief devices; 9 detectors; 50 alarm paths; operational turnover completed
Closed refrigeration project; PROMOTED ACTUAL HISTORY / ATTRIBUTION BOUNDED

TSK-000759 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000760 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000762 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000764 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000766 · Project delivery and operating readiness
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000768 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000770 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000771 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000772 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000773 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000774 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000775 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000776 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000777 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000778 · Control requirements
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000952 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000953 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-000954 · Action
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit

TSK-001071 · Safety control
Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit
Workstream Portfolio Rollup
5,695,000 USD
Environmental Compliance and Recovery Systems
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
| Measure or outcome | Value or result | Meaning and operating scope |
|---|---|---|
| Pre-Project Charge Estimate | 11,600 lb NH3 | Estimate Planning estimate Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Before field verification — Pre-project undocumented planning estimate |
| Field-Verified Installed Charge | 10,800 lb NH3 | Baseline Field-verified calculation Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Before Phase1–6 corrections — Field-verified calculated installed charge |
| Charge After Dead-Leg and Isolation Corrections | 10,152 lb NH3 | Observation Recorded condition Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit After Phase1–6 corrections — Documented charge after Phase 1-6 dead-leg/isolation corrections |
| Charge Reduction Through Dead-Leg and Isolation Corrections | 648 lb NH3 | Actual Result Achieved reduction Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Phase1–6 — Charge reduction achieved through Phase 1-6 corrections |
| Candidate Charge Reduction from Full Glycol-Conversion Option | 2,400 lb NH3 | Scenario or Model Result Potential reduction Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Full Phase7 option — Full Phase 7 candidate reduction if later executed |
| Potential Final Charge After Full Phase7 Execution | 7,752 lb NH3 | Scenario or Model Result Potential future charge Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Full Phase7 option — Potential final charge after full Phase 7 execution |
| Refrigeration P&ID Sheets Issued or Revised | 12 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Refrigeration P&ID sheets issued or revised |
| P&ID Verification Items | 250 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — P&ID verification items |
| Equipment Register Entries | 42 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Equipment register entries |
| Vessel/Nameplate Records | 14 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Vessel/nameplate records |
| Valve and Tag List Entries | 200 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Valve and tag list entries |
| Relief and Hydrostatic Relief Devices | 40 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Relief and hydrostatic relief devices |
| Ammonia Detectors | 9 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Ammonia detectors |
| Horn/Strobe/Alarm Devices | 11 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Horn/strobe/alarm devices |
| Emergency Ventilation and Shutdown Switches | 4 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Emergency ventilation and shutdown switches |
| Critical Valve Maps | 7 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Critical valve maps |
| Pipe Labels, Flow Arrows, Equipment Tags, Warning Signs | 320 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Pipe labels, flow arrows, equipment tags, warning signs |
| Mechanical-Integrity Findings | 80 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Mechanical-integrity findings |
| Condenser/Access/Guarding Findings | 18 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Condenser/access/guarding findings |
| Updated PM Tasks | 50 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Updated PM tasks |
| Controls I/O and Alarm Points Touched | 96 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Controls I/O and alarm points touched |
| Cause-and-Effect / Alarm-Response Test Paths | 50 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Cause-and-effect / alarm-response test paths |
| MOC Records | 20 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — MOC records |
| PSSR Records | 8 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — PSSR records |
| Personnel Requiring Training | 40 count | Scope or Inventory Quantity Field quantity basis Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Refrigeration retrofit scope — Personnel requiring training |
| Reduced Unplanned Refrigeration Interruptions | 78,000 USD/year | Scenario or Model Result Annual benefit component Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 12 avoided hours ×6,500USD/hour |
| Reduced Unplanned Refrigeration Interruptions — Quantity | 12 avoided hours/year | Scenario or Model Result Annualized benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 12 avoided hours ×6,500USD/hour |
| Reduced Unplanned Refrigeration Interruptions — Unit Rate | 6,500 USD/hour | Scenario or Model Result Benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 12 avoided hours ×6,500USD/hour |
| Avoided Emergency Contractor Call-Outs | 34,000 USD/year | Scenario or Model Result Annual benefit component Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 8 avoided call-outs ×4,250USD/call-out |
| Avoided Emergency Contractor Call-Outs — Quantity | 8 avoided call-outs/year | Scenario or Model Result Annualized benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 8 avoided call-outs ×4,250USD/call-out |
| Avoided Emergency Contractor Call-Outs — Unit Rate | 4,250 USD/call-out | Scenario or Model Result Benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 8 avoided call-outs ×4,250USD/call-out |
| Reduced PM and Troubleshooting Labor | 16,900 USD/year | Scenario or Model Result Annual benefit component Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 260hours ×65USD/hour |
| Reduced PM and Troubleshooting Labor — Quantity | 260 hours/year | Scenario or Model Result Annualized benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 260hours ×65USD/hour |
| Reduced PM and Troubleshooting Labor — Unit Rate | 65 USD/hour | Scenario or Model Result Benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 260hours ×65USD/hour |
| Insurance/Loss-Control/Compliance Reserve Reduction | 35,000 USD/year | Estimate Planning reserve component Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — $35,000/year fixed planning value for insurance, loss-control and compliance reserve reduction within the recorded $178,000 annual avoided-cost calculation. |
| Reduced Refrigerant Loss and Handling | 14,100 USD/year | Scenario or Model Result Annual benefit component Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 300lb ×47USD/lb |
| Reduced Refrigerant Loss and Handling — Quantity | 300 lb/year | Scenario or Model Result Annualized benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 300lb ×47USD/lb |
| Reduced Refrigerant Loss and Handling — Unit Rate | 47 USD/lb | Scenario or Model Result Benefit calculation input Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — 300lb ×47USD/lb |
| Total Annual Avoided-Cost Benefit | 178,000 USD/year | Scenario or Model Result Recorded annual avoided-cost calculation Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Annualized benefit calculation — Portfolio-recorded annual avoided-cost benefit of $178,000 combines $143,000 in interruption, contractor, labor and refrigerant benefit calculations with a $35,000 fixed planning reserve component. The portfolio describes the aggregate as actual benefit; the total therefore retains its mixed calculation and planning basis rather than representing $178,000 of realized cash savings. |
| Simple Payback | 5.056179775280899 years | Scenario or Model Result Calculated payback Applies to: Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit Installed-cost basis divided by annual benefit — Calculated simple payback: $900,000 budgeted installed-cost basis divided by the $178,000/year avoided-cost calculation equals 450/89 years (about 5.056). The denominator includes the $35,000 planning reserve component; this is not an observed payback period. |
| Recorded outcome | Refrigeration system corrections reduced documented ammonia charge by 648 lb. | Ammonia/Glycol Refrigeration Safety, Compliance, and Mechanical-Integrity Retrofit |
CASE-145 · Engineering case
Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
Read the Case ↗PRJ-B-008-SE-F1-001
FEL 1 / Concept · Business and decision documents · 2019-01-05 · PRJ-B-008-WBS-F1-01 · PRJ-B-008-BL-F1-B01
Establish the controlled business case and opportunity statement needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F1-002
FEL 1 / Concept · Business and decision documents · 2019-01-10 · PRJ-B-008-WBS-F1-02 · PRJ-B-008-BL-F1-B01
Establish the controlled project charter and initial scope / battery limits needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F1-003
FEL 1 / Concept · Reports · 2019-01-15 · PRJ-B-008-WBS-F1-03 · PRJ-B-008-BL-F1-B01
Establish the controlled stakeholder needs and operating context needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F1-004
FEL 1 / Concept · Studies and analyses · 2019-01-20 · PRJ-B-008-WBS-F1-04 · PRJ-B-008-BL-F1-B01
Establish the controlled concept alternatives and screening study needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F1-005
FEL 1 / Concept · Studies and analyses · 2019-01-25 · PRJ-B-008-WBS-F1-01 · PRJ-B-008-BL-F1-B01
Establish the controlled preliminary schedule and class 5 cost estimate needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F1-006
FEL 1 / Concept · Registers and indexes · 2019-01-30 · PRJ-B-008-WBS-F1-02 · PRJ-B-008-BL-F1-B01
Establish the controlled initial risk, assumption, and decision register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-001
FEL 2 / Select · Studies and analyses · 2019-02-04 · PRJ-B-008-WBS-F2-01 · PRJ-B-008-BL-F2-B01
Establish the controlled option study and weighted decision analysis needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-002
FEL 2 / Select · Design definitions · 2019-02-09 · PRJ-B-008-WBS-F2-02 · PRJ-B-008-BL-F2-B01
Establish the controlled design basis memorandum needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-003
FEL 2 / Select · Studies and analyses · 2019-02-15 · PRJ-B-008-WBS-F2-03 · PRJ-B-008-BL-F2-B01
Establish the controlled site, layout, and process alternative study needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-004
FEL 2 / Select · Specifications · 2019-02-20 · PRJ-B-008-WBS-F2-04 · PRJ-B-008-BL-F2-B01
Establish the controlled stakeholder and system requirements specification needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-005
FEL 2 / Select · Design definitions · 2019-02-25 · PRJ-B-008-WBS-F2-01 · PRJ-B-008-BL-F2-B01
Establish the controlled concept architecture and interface definition needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-006
FEL 2 / Select · Studies and analyses · 2019-03-03 · PRJ-B-008-WBS-F2-02 · PRJ-B-008-BL-F2-B01
Establish the controlled hazid / constructability / operability study needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-007
FEL 2 / Select · Studies and analyses · 2019-03-08 · PRJ-B-008-WBS-F2-03 · PRJ-B-008-BL-F2-B01
Establish the controlled class 4 estimate and level 2 schedule needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F2-008
FEL 2 / Select · Dossiers and manual sets · 2019-03-14 · PRJ-B-008-WBS-F2-04 · PRJ-B-008-BL-F2-B01
Establish the controlled selected concept and g2 decision dossier needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-001
FEL 3 / Define · Registers and indexes · 2019-03-19 · PRJ-B-008-WBS-F3-01 · PRJ-B-008-BL-F3-B01
Establish the controlled defined scope and design deliverables register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-002
FEL 3 / Define · Specifications · 2019-03-25 · PRJ-B-008-WBS-F3-02 · PRJ-B-008-BL-F3-B01
Establish the controlled baselined system requirements specification needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-003
FEL 3 / Define · Design definitions · 2019-03-30 · PRJ-B-008-WBS-F3-03 · PRJ-B-008-BL-F3-B01
Establish the controlled system architecture and interface control document needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-004
FEL 3 / Define · Plans · 2019-04-05 · PRJ-B-008-WBS-F3-04 · PRJ-B-008-BL-F3-B01
Establish the controlled project execution plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-005
FEL 3 / Define · Baselines and manifests · 2019-04-10 · PRJ-B-008-WBS-F3-01 · PRJ-B-008-BL-F3-B01
Establish the controlled wbs, work package, and responsibility baseline needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-006
FEL 3 / Define · Baselines and manifests · 2019-04-16 · PRJ-B-008-WBS-F3-02 · PRJ-B-008-BL-F3-B01
Establish the controlled class 3 estimate and cost baseline needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-007
FEL 3 / Define · Plans · 2019-04-21 · PRJ-B-008-WBS-F3-03 · PRJ-B-008-BL-F3-B01
Establish the controlled coordinated control schedule and resource plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-008
FEL 3 / Define · Plans · 2019-04-27 · PRJ-B-008-WBS-F3-04 · PRJ-B-008-BL-F3-B01
Establish the controlled procurement and contracting plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-009
FEL 3 / Define · Plans · 2019-05-02 · PRJ-B-008-WBS-F3-01 · PRJ-B-008-BL-F3-B01
Establish the controlled v&v, acceptance, commissioning, and turnover strategy needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-F3-010
FEL 3 / Define · Certificates and approvals · 2019-05-08 · PRJ-B-008-WBS-F3-02 · PRJ-B-008-BL-F3-B01
Establish the controlled fid / g3 approval and baseline manifest needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-001
Detailed Design · Plans · 2019-05-13 · PRJ-B-008-WBS-DD-01 · PRJ-B-008-BL-DD-B01
Establish the controlled detailed design management plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-002
Detailed Design · Design definitions · 2019-05-19 · PRJ-B-008-WBS-DD-02 · PRJ-B-008-BL-DD-B01
Establish the controlled process / functional design package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-003
Detailed Design · Design definitions · 2019-05-24 · PRJ-B-008-WBS-DD-03 · PRJ-B-008-BL-DD-B01
Establish the controlled mechanical and piping design package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-004
Detailed Design · Design definitions · 2019-05-30 · PRJ-B-008-WBS-DD-04 · PRJ-B-008-BL-DD-B01
Establish the controlled electrical power and controls design package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-005
Detailed Design · Design definitions · 2019-06-04 · PRJ-B-008-WBS-DD-01 · PRJ-B-008-BL-DD-B01
Establish the controlled civil, structural, and architectural design package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-006
Detailed Design · Design definitions · 2019-06-10 · PRJ-B-008-WBS-DD-02 · PRJ-B-008-BL-DD-B01
Establish the controlled instrumentation, automation, and data design package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-007
Detailed Design · Studies and analyses · 2019-06-15 · PRJ-B-008-WBS-DD-03 · PRJ-B-008-BL-DD-B01
Establish the controlled safety, reliability, and maintainability analysis needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-008
Detailed Design · Records and logs · 2019-06-21 · PRJ-B-008-WBS-DD-04 · PRJ-B-008-BL-DD-B01
Establish the controlled design review and comment resolution record needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-009
Detailed Design · Baselines and manifests · 2019-06-26 · PRJ-B-008-WBS-DD-01 · PRJ-B-008-BL-DD-B01
Establish the controlled issued-for-construction design baseline needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-DD-010
Detailed Design · Registers and indexes · 2019-07-02 · PRJ-B-008-WBS-DD-02 · PRJ-B-008-BL-DD-B01
Establish the controlled design v&v evidence index needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-001
Procurement · Registers and indexes · 2019-07-07 · PRJ-B-008-WBS-PR-01 · PRJ-B-008-BL-PR-B01
Establish the controlled procurement package and bid list needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-002
Procurement · Specifications · 2019-07-13 · PRJ-B-008-WBS-PR-02 · PRJ-B-008-BL-PR-B01
Establish the controlled technical requisition and datasheet set needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-003
Procurement · Studies and analyses · 2019-07-19 · PRJ-B-008-WBS-PR-03 · PRJ-B-008-BL-PR-B01
Establish the controlled commercial bid evaluation and award recommendation needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-004
Procurement · Registers and indexes · 2019-07-24 · PRJ-B-008-WBS-PR-04 · PRJ-B-008-BL-PR-B01
Establish the controlled technical bid evaluation and clarification log needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-005
Procurement · Business and decision documents · 2019-07-30 · PRJ-B-008-WBS-PR-01 · PRJ-B-008-BL-PR-B01
Establish the controlled purchase order / contract and scope of supply needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-006
Procurement · Plans · 2019-08-05 · PRJ-B-008-WBS-PR-02 · PRJ-B-008-BL-PR-B01
Establish the controlled supplier quality and inspection plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-007
Procurement · Registers and indexes · 2019-08-10 · PRJ-B-008-WBS-PR-03 · PRJ-B-008-BL-PR-B01
Establish the controlled vendor data, submittal, and rfi register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-008
Procurement · Plans · 2019-08-16 · PRJ-B-008-WBS-PR-04 · PRJ-B-008-BL-PR-B01
Establish the controlled expediting and logistics plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-PR-009
Procurement · Procedures · 2019-08-22 · PRJ-B-008-WBS-PR-01 · PRJ-B-008-BL-PR-B01
Establish the controlled factory acceptance test procedure and report needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-001
Fabrication / Construction · Plans · 2019-08-30 · PRJ-B-008-WBS-FC-01 · PRJ-B-008-BL-FC-B01
Establish the controlled construction / fabrication execution plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-002
Fabrication / Construction · Plans · 2019-09-08 · PRJ-B-008-WBS-FC-02 · PRJ-B-008-BL-FC-B01
Establish the controlled site logistics, safety, and permit plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-003
Fabrication / Construction · Design definitions · 2019-09-16 · PRJ-B-008-WBS-FC-03 · PRJ-B-008-BL-FC-B01
Establish the controlled fabrication drawing and shop package needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-004
Fabrication / Construction · Procedures · 2019-09-25 · PRJ-B-008-WBS-FC-04 · PRJ-B-008-BL-FC-B01
Establish the controlled field work package and installation method needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-005
Fabrication / Construction · Plans · 2019-10-03 · PRJ-B-008-WBS-FC-01 · PRJ-B-008-BL-FC-B01
Establish the controlled inspection and test plan / quality records needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-006
Fabrication / Construction · Records and logs · 2019-10-12 · PRJ-B-008-WBS-FC-02 · PRJ-B-008-BL-FC-B01
Establish the controlled daily progress and quantity report needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-007
Fabrication / Construction · Records and logs · 2019-10-20 · PRJ-B-008-WBS-FC-03 · PRJ-B-008-BL-FC-B01
Establish the controlled nonconformity and corrective action record needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-008
Fabrication / Construction · Registers and indexes · 2019-10-29 · PRJ-B-008-WBS-FC-04 · PRJ-B-008-BL-FC-B01
Establish the controlled redline drawing and field change register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-FC-009
Fabrication / Construction · Certificates and approvals · 2019-11-07 · PRJ-B-008-WBS-FC-01 · PRJ-B-008-BL-FC-B01
Establish the controlled mechanical completion certificate and punch list needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-001
Installation and Interface Coordination · Plans · 2019-11-12 · PRJ-B-008-WBS-IN-01 · PRJ-B-008-BL-IN-B01
Establish the controlled system coordination and interface plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-002
Installation and Interface Coordination · Records and logs · 2019-11-17 · PRJ-B-008-WBS-IN-02 · PRJ-B-008-BL-IN-B01
Establish the controlled installation completion and walkdown record needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-003
Installation and Interface Coordination · Baselines and manifests · 2019-11-23 · PRJ-B-008-WBS-IN-03 · PRJ-B-008-BL-IN-B01
Establish the controlled controls / software configuration baseline needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-004
Installation and Interface Coordination · Records and logs · 2019-11-28 · PRJ-B-008-WBS-IN-04 · PRJ-B-008-BL-IN-B01
Establish the controlled loop check, continuity, and calibration records needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-005
Installation and Interface Coordination · Procedures · 2019-12-04 · PRJ-B-008-WBS-IN-01 · PRJ-B-008-BL-IN-B01
Establish the controlled cleaning, flushing, and pre-operational test record needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-006
Installation and Interface Coordination · Dossiers and manual sets · 2019-12-09 · PRJ-B-008-WBS-IN-02 · PRJ-B-008-BL-IN-B01
Establish the controlled system completion dossier needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-IN-007
Installation and Interface Coordination · Certificates and approvals · 2019-12-15 · PRJ-B-008-WBS-IN-03 · PRJ-B-008-BL-IN-B01
Establish the controlled ready-for-commissioning certificate needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-001
Commissioning / Startup · Plans · 2019-12-20 · PRJ-B-008-WBS-CS-01 · PRJ-B-008-BL-CS-B01
Establish the controlled commissioning and startup plan needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-002
Commissioning / Startup · Reports · 2019-12-25 · PRJ-B-008-WBS-CS-02 · PRJ-B-008-BL-CS-B01
Establish the controlled pre-startup safety / operational readiness review needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-003
Commissioning / Startup · Procedures · 2019-12-30 · PRJ-B-008-WBS-CS-03 · PRJ-B-008-BL-CS-B01
Establish the controlled commissioning procedure and results needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-004
Commissioning / Startup · Registers and indexes · 2020-01-04 · PRJ-B-008-WBS-CS-04 · PRJ-B-008-BL-CS-B01
Establish the controlled startup and ramp-up log needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-005
Commissioning / Startup · Studies and analyses · 2020-01-10 · PRJ-B-008-WBS-CS-01 · PRJ-B-008-BL-CS-B01
Establish the controlled performance guarantee and capacity test report needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-006
Commissioning / Startup · Studies and analyses · 2020-01-15 · PRJ-B-008-WBS-CS-02 · PRJ-B-008-BL-CS-B01
Establish the controlled reliability demonstration run report needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-007
Commissioning / Startup · Records and logs · 2020-01-20 · PRJ-B-008-WBS-CS-03 · PRJ-B-008-BL-CS-B01
Establish the controlled operator and maintainer training record needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-008
Commissioning / Startup · Registers and indexes · 2020-01-25 · PRJ-B-008-WBS-CS-04 · PRJ-B-008-BL-CS-B01
Establish the controlled commissioning anomaly and punch closure register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-CS-009
Commissioning / Startup · Certificates and approvals · 2020-01-31 · PRJ-B-008-WBS-CS-01 · PRJ-B-008-BL-CS-B01
Establish the controlled performance acceptance certificate needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-001
Operational Turnover / Closeout · Baselines and manifests · 2020-02-03 · PRJ-B-008-WBS-OT-01 · PRJ-B-008-BL-OT-B01
Establish the controlled as-built / as-configured baseline manifest needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-002
Operational Turnover / Closeout · Dossiers and manual sets · 2020-02-07 · PRJ-B-008-WBS-OT-02 · PRJ-B-008-BL-OT-B01
Establish the controlled operations and maintenance manual set needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-003
Operational Turnover / Closeout · Registers and indexes · 2020-02-10 · PRJ-B-008-WBS-OT-03 · PRJ-B-008-BL-OT-B01
Establish the controlled asset, spare parts, and warranty register needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-004
Operational Turnover / Closeout · Certificates and approvals · 2020-02-14 · PRJ-B-008-WBS-OT-04 · PRJ-B-008-BL-OT-B01
Establish the controlled final technical and commercial acceptance certificate needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-005
Operational Turnover / Closeout · Dossiers and manual sets · 2020-02-18 · PRJ-B-008-WBS-OT-01 · PRJ-B-008-BL-OT-B01
Establish the controlled operational turnover dossier and ownership transfer needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-006
Operational Turnover / Closeout · Studies and analyses · 2020-02-21 · PRJ-B-008-WBS-OT-02 · PRJ-B-008-BL-OT-B01
Establish the controlled final cost, schedule, contract, and claims closeout needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-007
Operational Turnover / Closeout · Registers and indexes · 2020-02-25 · PRJ-B-008-WBS-OT-03 · PRJ-B-008-BL-OT-B01
Establish the controlled controlled records archive and retrieval index needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.
PRJ-B-008-SE-OT-008
Operational Turnover / Closeout · Baselines and manifests · 2020-02-29 · PRJ-B-008-WBS-OT-04 · PRJ-B-008-BL-OT-B01
Establish the controlled lessons learned and benefit realization baseline needed to execute Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Ammonia/glycol refrigeration system within PRJ-B-008 - Ammonia/Glycol Refrigeration Safety, Compliance, and MI Retrofit. The project scope is: P&ID recovery, charge calculation, IIAR 9 evaluation, machinery-room safety, relief validation, mechanical integrity, glycol review, controls, PM alignment, MOC/PSSR, testing, training, and turnover. Documented and accepted refrigeration system with corrected safeguards, verified relief protection, closed MI findings, reduced charge, and operating ownership.