TSK-000081 · Pilot scope

Planned Decanter Trial Setup and Temporary Utilities

Explore the capability, case, and equipment connections for this activity.

Conceptual engineering illustration: field quality
Conceptual engineering visualization · AI generated

Activity Detail

Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids.

Case Context

Rice Wine Decanter Trial ↗

Capabilities

Systems & Equipment

Measures & Operating Context

MeasureValueType & meaningAttribution & operating context
Active Test Duration3 daysTarget
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Planned active trial — Active test duration — Planned active trial

Temporary Electrical Circuit60 AEquipment Rating
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Existing three-phase supply — Temporary electrical circuit — Existing three-phase supply

CIP Solution Volume250 galDesign Parameter
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Planned trial cleaning — CIP solution volume — Planned trial cleaning

All Portfolio Connections

All portfolio connections (10)

Related Analysis and Application Artifacts

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗