WORK CONTEXT
Rice Wine Decanter Trial
Follow the connected work in the portfolio.

Roles & Contributions
Project Ownership
Full lifecycle project ownership
Project Leadership
Owned the planned decanter pilot scope, including temporary integration, testing, resources and implementation planning.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Project Stakeholder
Oversight
Named Project Responsibility
Named oversight responsibility for the planned rice-wine decanter pilot.
Project Stakeholder
Process Owner
Named Project Responsibility
Named process-owner responsibility for the planned rice-wine decanter pilot.
Connected Work
All portfolio connections (16)
- Rice Wine Decanter Trialdescribed byRice Wine Decanter Trial ↗
- Rice Wine Decanter Trialincludes taskDeveloped and Owned the Scope for a Modular Rice-Wine Decanter Pilot to Evaluate Replacement of an End-of-Life Filter Press Before Capital Commitment ↗
- Rice Wine Decanter Trialincludes taskPlanned Decanter Trial Setup and Temporary Utilities ↗
- Rice Wine Decanter Trialincludes taskDefined Onsite Trial Measurements for Turbidity, Solids Concentration, Product Recovery, Wine Loss, Water, Electrical Use, Waste Volume and Operator Labor ↗
- Rice Wine Decanter Trialincludes taskCompared an Estimated 50–75% Capital-Cost Advantage and Four-to-Five-Times Longer Rebuild Intervals with Separator-Style Alternatives, Alongside a Planned Three-to-Four-Week Post-Order Pilot Window ↗
- Rice Wine Decanter Trialincludes taskPlanned Temporary Tri-Clamp and Camlock Connections, Sanitary Sampling Valves, Hoses, Drain Routing, CIP Adaptation, Flow Measurement, HMI Access, Vendor Laboratory Support and ROI/TCO Evaluation ↗
- Rice Wine Decanter Trialincludes taskDefined and Submitted the Unfiltered Rice-Wine Sample and Process Basis to Decanter Supplier, Including the Recovery Target for a Feasibility Study ↗
- Rice Wine Decanter Trialprocesses productRice Wine and Sake ↗
- Rice Wine Decanter Trialincludes taskDecanter Supplier Characterized the Rice-Wine Sample, Varied g-Force and Residence Time, Found Decanter and Sedicanter Separation Feasible, and Recommended Dynamic Pilot Testing at the Required Clarity and Throughput ↗
- Rice Wine Decanter Trialincludes taskSigned the Revised Z3E Trial Agreement on 24 July 2025 After Sample Definition, Feasibility Review and Temporary-Integration Planning; the Trial Start Date Remained to Be Set ↗
- Rice Wine Decanter Trialincludes taskEvaluated the C3E 4/454 Proposal as a Capital Option, Including the Two-Phase Bowl and Scroll, Contact Materials, Wear Protection, Drives, Controls, Monitoring, Optional Feed/Centrate Integration and Commercial Schedule ↗
- Rice Wine Decanter Trialincludes taskDecanter Pilot Feed and Performance-Test Plan ↗
- Rice Wine Decanter Trialincludes taskDecanter Pilot Solids and Caustic Containment ↗
- Rice Wine Decanter Trialincludes taskPlanned an Onsite Lab Station with a Laboratory Centrifuge, Oven, Scale and Turbidity Meter to Evaluate Filtrate Clarity, Solids Concentration and Wine Loss While Tuning Feedrate and Separation ↗
- Rice Wine Decanter Trialincludes taskDecanter Feasibility and Investment-Decision Deliverables ↗
- Rice Wine Decanter Trialincludes taskRice-Wine Feasibility-Sample Definition and Handling ↗