CASE-041 · Engineering case

Rice Wine Decanter Trial

Evaluate rice-wine filter-press replacement through sample definition, vendor feasibility work and a planned modular decanter trial.

Conceptual engineering visualization: Rice Wine Decanter Trial
Conceptual engineering visualization · AI generated

Why the Work Mattered

Purpose and Operating Need

Evaluate replacement of the filter press through vendor laboratory feasibility and temporary trial planning before full-scale equipment selection.

Engineering Approach

Engineering Approach

Temporary sanitary integration, utilities, sampling and cleaning scope, equipment-option review and trial authorization.

Outcome & Engineering Context

Outcome and Context

Advanced the work through vendor laboratory feasibility and a signed revised Z3E trial agreement dated 24 July 2025; the site trial start remained to be set.

Workstream Results & Impact

Workstream Portfolio Rollup

18,317,000 USD

Wine Clarification and Vinegar Polishing Modernization

Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.

Measures & Operating Detail

MeasureValueType & meaningAttribution & operating context
Planned CIP Caustic Concentration1 %Design Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

Temporary trial cleaning — 1% caustic at 140°F

Planned CIP Temperature140 degFDesign Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

Temporary trial cleaning — 1% caustic at 140°F

Estimated Decanter Capital-Cost Advantage50 to 75 %Estimate
Estimated option benefit

Applies to: Rice Wine Decanter Trial

Decanter versus separator comparison — estimated 50%–75% capital-cost advantage

Active Pilot Testing3 daysTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

Planned active trial — Active pilot testing

CIP Solution Batch Volumeapproximately 250 US galDesign Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

Prepared in filter feed tank — CIP solution batch volume

Initial Acid-Neutralizing CIP Volumeapproximately 50 US galDesign Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

First flush portion — Initial acid-neutralizing CIP volume

Expected Remaining Spent-CIP pH11 to 12 pH unitsEstimate
Planned trial input

Applies to: Rice Wine Decanter Trial

After initial acid neutralization — Expected remaining spent-CIP pH

Pilot Stand Height40 inDesign Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

Solids tote fit — Pilot stand height

Planned Tote Top Removal10 inDesign Parameter
Planned trial input

Applies to: Rice Wine Decanter Trial

Solids tote fit — Planned tote top removal

Solids-Capture Tote Capacity250 US galEquipment Rating
Planned trial input

Applies to: Rice Wine Decanter Trial

Pilot waste handling — Solids-capture tote capacity

Available Pilot Circuit Current60 AEquipment Rating
Existing electrical circuit rating

Applies to: Rice Wine Decanter Trial

Existing three-phase circuit — Available pilot circuit current

Estimated Relative Rebuild Interval4 to 5 xEstimate
Estimated option benefit

Applies to: Rice Wine Decanter Trial

Decanter versus separator comparison — Estimated relative rebuild interval

Potential Fermenter-Space Allowance2 to 3 fermentersEstimate
Estimated option benefit

Applies to: Rice Wine Decanter Trial

Potential footprint benefit — Potential fermenter-space allowance

Expected CIP Operator Attentionapproximately 30 minEstimate
Estimated option benefit

Applies to: Rice Wine Decanter Trial

Proposed decanter cleaning — Expected CIP operator attention

Planned Pilot Equipment Lead Time3 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

After purchase order — Planned pilot equipment lead time

Planned Preinstallation Window2 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

Overlapping equipment delivery — Planned preinstallation window

Planned Setup and Testing Window1 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

Installation commissioning testing — Planned setup and testing window

Planned Overall Pilot Implementation3 to 4 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

After purchase order — Planned overall pilot implementation

Minimum Pretest Onsite Availability>= 2 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

Before active trial — Minimum pretest onsite availability

Minimum Post-Test Onsite Availability>= 2 weeksTarget
Planned trial input

Applies to: Rice Wine Decanter Trial

After active trial — Minimum post-test onsite availability

Active Test Duration3 daysTarget
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Planned active trial — Active test duration — Planned active trial

Temporary Electrical Circuit60 AEquipment Rating
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Existing three-phase supply — Temporary electrical circuit — Existing three-phase supply

CIP Solution Volume250 galDesign Parameter
Planned trial input

Applies to: Specified a planned three-day trial using an existing 60 A three-phase circuit and filter-press feed pump, temporary sanitary product/CIP/waste connections, and approximately 250 gallons of 1% caustic at 140°F prepared in the existing filter feed tank; a separate modified tote captures solids

Planned trial cleaning — CIP solution volume — Planned trial cleaning

Post-Order Implementation Window3 to 4 weeksTarget
Planned trial input

Applies to: Compared an estimated 50–75% capital-cost advantage and four-to-five-times longer rebuild intervals with separator-style alternatives, alongside a planned three-to-four-week post-order pilot window

Pilot preparation — Post-order implementation window — Pilot preparation

Rebuild Interval Multiplier4 to 5 timesEstimate
Estimated option benefit

Applies to: Compared an estimated 50–75% capital-cost advantage and four-to-five-times longer rebuild intervals with separator-style alternatives, alongside a planned three-to-four-week post-order pilot window

Compared with separator alternatives — Rebuild interval multiplier — Compared with separator alternatives

Feed Alcohol Content16 %Design Parameter
Sample specification

Applies to: Defined and submitted the unfiltered rice-wine sample and process basis to decanter supplier, including the recovery target for a feasibility study

Unfiltered rice wine after fermentation — Feed alcohol content — Unfiltered rice wine after fermentation

Process Flow Basis7,000 GPDDesign Parameter
Design basis

Applies to: Defined and submitted the unfiltered rice-wine sample and process basis to decanter supplier, including the recovery target for a feasibility study

Feasibility submission — Process flow basis — Feasibility submission

Product Recovery> 90 %Target
Trial target

Applies to: Defined and submitted the unfiltered rice-wine sample and process basis to decanter supplier, including the recovery target for a feasibility study

Feasibility submission — Product recovery — Feasibility submission

Sample Collection Temperature80 °FObservation
Sample specification

Applies to: Defined and submitted the unfiltered rice-wine sample and process basis to decanter supplier, including the recovery target for a feasibility study

14 August 2024 post-fermentation/pre-filtration — Sample collection temperature

Recovery Target Priority1 rankTarget
Trial target

Applies to: Defined and submitted the unfiltered rice-wine sample and process basis to decanter supplier, including the recovery target for a feasibility study

Feasibility submission — Recovery target priority

pH4 pH unitsObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — pH — Decanter supplier rice-wine sample, 20 August 2024

Brix12 °BxObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Brix — Decanter supplier rice-wine sample, 20 August 2024

Density1.007 g/mLObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Density — Decanter supplier rice-wine sample, 20 August 2024

Total Solids8.47 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Total solids — Decanter supplier rice-wine sample, 20 August 2024

Suspended Solids3.06 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Suspended solids — Decanter supplier rice-wine sample, 20 August 2024

Dissolved Solids5.41 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Dissolved solids — Decanter supplier rice-wine sample, 20 August 2024

Spin Index2.2 reported indexObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Spin index — Decanter supplier rice-wine sample, 20 August 2024

Laboratory Test Temperature23 °CDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine feasibility — Laboratory test temperature

Total Solids85,217 mg/LObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Total solids

Suspended Solids30,767 mg/LObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Suspended solids

Dissolved Solids54,450 mg/LObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Decanter supplier rice-wine sample, 20 August 2024 — Dissolved solids

Particle-Size Median263.35049 µmObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Printed median 263.35049 µm; the same D50 statistic is printed 263.3505 µm in the cumulative table, so it is retained as one observation.

Particle-Size Mean343.91736 µmObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Particle-size mean read from the embedded analyzer image; median/D50 retain their printed precision

Particle-Size Mode482.8425 µmObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Particle-size mode read from the embedded analyzer image; median/D50 retain their printed precision

Particle Diameter at 10% Cumulative6.6742 µmObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Particle diameter at 10% cumulative read from the embedded analyzer image; median/D50 retain their printed precision

Particle Diameter at 90% Cumulative803.8865 µmObservation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Particle diameter at 90% cumulative read from the embedded analyzer image; median/D50 retain their printed precision

Analyzer Transmittance R91.9 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Analyzer transmittance R

Analyzer Transmittance B92.3 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Laboratory-instrument supplier LA-960 analysis of rice-wine feed — Analyzer transmittance B

Cumulative Particle Distribution73.166 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 500 µm — Printed cumulative undersize at 500 µm

Cumulative Particle Distribution29.487 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 100 µm — Printed cumulative undersize at 100 µm

Cumulative Particle Distribution20.91 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 50 µm — Printed cumulative undersize at 50 µm

Cumulative Particle Distribution17.838 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 20 µm — Printed cumulative undersize at 20 µm

Cumulative Particle Distribution15.266 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 10 µm — Printed cumulative undersize at 10 µm

Cumulative Particle Distribution5.111 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 5 µm — Printed cumulative undersize at 5 µm

Cumulative Particle Distribution0 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 1 µm — Printed cumulative undersize at 1 µm

Cumulative Particle Distribution0 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 0.5 µm — Printed cumulative undersize at 0.5 µm

Cumulative Particle Distribution0 %Observation
Vendor laboratory result

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Undersize at 0.2 µm — Printed cumulative undersize at 0.2 µm

Test Centrifugal Acceleration1,000 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 1 — Test centrifugal acceleration

Test Residence Time1 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 1 — Test residence time

Test Centrifugal Acceleration1,000 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 2 — Test centrifugal acceleration

Test Residence Time5 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 2 — Test residence time

Test Centrifugal Acceleration3,000 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 3 — Test centrifugal acceleration

Test Residence Time1 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 3 — Test residence time

Test Centrifugal Acceleration3,000 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 4 — Test centrifugal acceleration

Test Residence Time2 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 4 — Test residence time

Test Centrifugal Acceleration3,000 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 5 — Test centrifugal acceleration

Test Residence Time5 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 5 — Test residence time

Test Centrifugal Acceleration4,900 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 6 — Test centrifugal acceleration

Test Residence Time5 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 6 — Test residence time

Test Centrifugal Acceleration6,500 gDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 7 — Test centrifugal acceleration

Test Residence Time5 minDesign Parameter
Vendor laboratory test condition

Applies to: Decanter supplier characterized the rice-wine sample, varied g-force and residence time, found decanter and sedicanter separation feasible, and recommended dynamic pilot testing at the required clarity and throughput

Photographed spin condition 7 — Test residence time

Bowl Diameter14.5 inDesign Parameter
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Bowl — Bowl diameter — Bowl

Rotational Speed<= 4,000 rpmEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Rated maximum — Rotational speed — Rated maximum

Centrifugal Acceleration<= 3,300 gEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Rated maximum — Centrifugal acceleration — Rated maximum

Motor Power20 HPEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Bowl drive — Motor power — Bowl drive

Motor Power5 HPEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Scroll drive — Motor power — Scroll drive

HMI Display Size10 inDesign Parameter
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

operator display — HMI display size — operator display

Engineering Submittal Lead Time10 weeksEstimate
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

After order acceptance — Engineering submittal lead time — After order acceptance

Onsite Service Allowance10 daysQuotation
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Proposal service — Onsite service allowance — Proposal service

Equipment Delivery Lead Time30 to 34 weeksEstimate
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

After order acceptance — Equipment delivery lead time — After order acceptance

Scroll Speed1 to 10 rpmEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Scroll drive — Scroll speed

Continuous Scroll Torque2,750 N mEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Scroll reducer — Continuous scroll torque

Vendor Stated Bowl-Power Reductionapproximately 20 %Estimate
Vendor-projected bowl-power reduction

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Recuvane option — Decanter supplier proposal estimates approximately 20% bowl-motor power reduction for the Recuvane option; not a measured site energy saving.

Supply Phase Count3 phasesEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Electrical supply — Supply phase count

Supply Frequency60 HzEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Electrical supply — Supply frequency

Supply Voltage480 VEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Electrical supply — Supply voltage

Approximate Unit Weightapproximately 3,900 lbEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

C3E option — Approximate unit weight

Submittal Review Allowance2 weeksEstimate
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

After engineering submittal — Submittal review allowance

Illustrated Centrate-Tank Capacity130 US galEquipment Rating
Vendor proposal

Applies to: Evaluated the C3E 4/454 proposal as a capital option, including the two-phase bowl and scroll, contact materials, wear protection, drives, controls, monitoring, optional feed/centrate integration and commercial schedule

Z3E 4/454 arrangement drawing — Illustrated centrate-tank capacity

Engineering scope and design basis

Developed a pilot decanter trial to evaluate replacement of an end-of-life rice wine filter press.

Created a pilot plan to evaluate product recovery before full-scale capital commitment.

Included filter-press consumable reduction as an objective of the planned trial.

Included waste reduction as an objective of the planned trial.

Included water and electrical-use reduction as objectives of the planned trial.

Included operator-labor reduction as an objective of the planned trial.

Planned to use existing utilities for the onsite trial.

Planned temporary hose connections for the onsite trial.

Used vendor laboratory feasibility findings to inform onsite trial planning.

Planned vendor-supported onsite testing before full-scale capital selection.

Developed the modular decanter supplier rice-wine decanter pilot scope to evaluate replacement of the end-of-life filter press.

Specified a self-contained modular pilot skid for the planned onsite evaluation.

Planned a three-day active trial using the existing 60 A three-phase circuit and filter-press feed pump.

Planned temporary camlock and tri-clamp product, cleaning and waste connections.

Specified preparation of 250 gallons of cleaning solution in the existing filter-feed tank.

Specified a cleaning solution of 1% caustic at 140°F.

Defined turbidity measurement for the planned onsite trial.

Defined solids-concentration measurement for the planned onsite trial.

Defined wine-loss measurement for the planned onsite trial.

Compared an estimated decanter capital cost 50-75% below separator-style alternatives.

Compared estimated decanter rebuild intervals four to five times longer than separator-style alternatives.

Included no-cost vendor laboratory support in the pilot evaluation.

Planned a three-to-four-week post-purchase-order mobilization window.

Developed a planned three-day decanter trial using the existing 60 A circuit and filter-press feed infrastructure.

Defined turbidity testing for the planned onsite trial.

Defined solids-concentration testing for the planned onsite trial.

Defined wine-loss testing before full-scale capital commitment.

Improved filtration replacement decision quality and pilot readiness.

Planned three-day active onsite trial.

Planned three-to-four-week post-purchase-order mobilization window.

Existing 60 A circuit identified for the planned trial.

250 gallons of cleaning solution to be prepared in the existing filter-feed tank; the modified tote was for solids/waste collection.

Specified cleaning concentration and temperature: 1% caustic at 140°F.

Estimated decanter capital-cost advantage of 50-75% versus separator-style alternatives.

Estimated rebuild intervals four to five times longer than separator-style alternatives.

Planned use of a modular, self-contained decanter skid.

Planned use of the existing feed pump and power circuit.

Planned temporary sanitary product, cleaning and waste connections.

Defined onsite laboratory testing for the planned trial.

Coordinated supplier support for feasibility and onsite-trial preparation.

Planned ROI comparison to support the capital decision.

Actions, Methods & Controls

ACTIVITIES IN CONTEXT

Additional Technical Detail

Roles & contributions
  • Project Ownership

    Full lifecycle project ownership

    Project Leadership

    Owned the planned decanter pilot scope, including temporary integration, testing, resources and implementation planning.

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

  • Project Stakeholder

    Oversight

    Named Project Responsibility

    Named oversight responsibility for the planned rice-wine decanter pilot.

  • Project Stakeholder

    Process Owner

    Named Project Responsibility

    Named process-owner responsibility for the planned rice-wine decanter pilot.

  • Project and Plant Team

    Project coordination

    Project coordination

    The trial plan named Project stakeholder for oversight and Project stakeholder as process owner; operators, QA and maintenance appear in the existing rice-room process map.

  • Decanter Supplier

    Supplier Participation

    Vendor Contribution

    Decanter supplier performed laboratory feasibility, characterized solids/particle size and recommended piloting; Laboratory technician was laboratory technician and Supplier sales manager sales manager. Decanter supplier supplies the planned trial skid/stand.

Workstream context
Additional technical detail
Explore 29 detail records
  • Decision

    Planned the onsite trial around existing utilities, temporary hose connections, completed vendor laboratory feasibility and vendor-supported pilot testing before full-scale capital selection.

  • Measure

    The planned three-day decanter trial uses the existing 60 A circuit and feed pump, with a three-to-four-week post-order mobilization target. The existing filter-feed tank prepares 250 gallons of 1% caustic at 140°F; a modified tote receives solids and drainage. Capital-cost and rebuild-interval comparisons remain supplier alternatives.

  • Laboratory method

    The 20 August 2024 Decanter supplier laboratory tested received unfiltered rice wine at 23°C. It dried and filtered material for solids characterization, considered metallurgy-limiting chemistry, varied g-force and residence time in a laboratory centrifuge, examined sediment conveyability, and used a laboratory-instrument supplier LA-960 laser-scattering analyzer for particle-size distribution. Laboratory technician was laboratory technician; Supplier sales manager sales manager; customer contact.

  • Laboratory interpretation

    The sediment was described as conveyable; clarity and compaction improved with increasing g-force and residence time. Decanter supplier judged decanter and sedicanter feasible, with possible decanter turbidity at moderate/high feed rates; it suggested low-feed decanter, sedicanter, or a second disc-stack clarification step according to clarity needs. Static-tube centrate is a best-case and submerged sediment may be a worst-case relative to a dynamic scroll machine; actual performance requires piloting. Phase-volume cells in the photographed test table are blank, so no phase percentages were inferred.

  • Equipment option detail

    C3E option review includes fume-tight two-phase duty, adjustable weirs and Recuvane energy-recovery weirs; wear-protected 316/duplex contact components; independent variable scroll/bowl drives; condition and torque monitoring; automatic lubrication; UL/NEMA panel choices; feed-flow feedback and production trending; centrate and solids-discharge integration. These are vendor-supplied selection requirements.

  • Layout context

    Proposal drawings include C3E general arrangement and support stand, a generic control enclosure and operator enclosure, and a Z3E 4/454 system illustration with 130-gallon sloped-bottom centrate tank, inspection hatch, level sensor, sprayball, drain, sightglass, sample port and conveyor. Generic panel titleblocks retain PXXXXX/customer placeholders; the Z3E illustrated arrangement is not relabeled as an installed C3E.

  • Commercial option detail

    Proposal includes ten onsite service days, estimated 10-week engineering submittal with two weeks allotted for approval, estimated 30–34-week delivery after acceptance, electronic operation/maintenance manuals, staged 25%/25%/40%/10% payment and Net 30 after initial payment. Warranty expires at the earlier of 12 months operation or 18 months delivery; proposal validity is 60 days.

  • Temporary integration scope

    The temporary scope uses an existing 60 A three-phase circuit, temporary power lead, camlock/tri-clamp product-water-CIP-air connections, filtered water/air lines with manual gauges, and the existing feed pump/control panel for data capture. Permanent utilities, full-scale procurement, structural modification/demolition and offsite waste disposal are excluded. Installation/removal anticipates a few hours with no shutdown unless EHS requires one.

  • Pilot cleaning and waste plan

    CIP plan: approximately 250 gallons of 1% caustic at 140°F mixed/heated in the existing filter feed tank and pumped once through; initial 50 gallons neutralize wine acidity, remaining waste expected around pH 11–12 needs EHS disposition. Close the solids-tote valve and handle solution separately if wastewater discharge is not permitted. These are case-specific planning values.

  • Pilot material and utility list

    Food and beverage manufacturer material list: one 20 ft × 2 in camlock hose, two 50 ft × 2 in camlock hoses, one 250 gal tote with bottom valve (top 10 in removed), two 50 gal barrels, 100 ft of 3/8 in air tubing and quick connects, two 50 ft garden hoses, 1.5 in-to-2 in tri-clamp reducers, at least two 1.5 in clamp/gasket sets, additional 2 in clamps/gaskets, one 2 in sanitary tee, two 2 in elbows, and one 2 in camlock-to-tri-clamp adapter. Decanter supplier supplies skid and stand.

  • Pilot schedule

    Scope 30 June 2025: three active days with decanter supplier technician; equipment onsite at least two weeks before and after for flexibility; equipment lead time 3 weeks after PO, overlapping 2-week preinstallation window, and 1 week installation/commissioning/testing, with 3–4 week overall post-PO duration. These are planned durations.

  • Sample and design basis

    Sample collected 14 August 2024 at 80°F after fermentation before filtration: 16% unfiltered rice wine, water/milled rice/yeast/enzymes, rice wine and mash, chilled storage, and municipal wastewater disposal context. Form marks 2-phase decanter and belt-press feasibility; specifies 7000 GPD, ambient desired temperature, ambient ±5°F maximum condition, no upstream conditioning, no permitted additives, no flammability hazard and no pressurization during filtration. Several feed properties were explicitly unknown at this time.

  • Trial acceptance target

    The completed submission makes recovery the priority-1 target, >90%, measured by liquid volume before and after. Required-clarity cells are blank; discharge pH is to be similar to feed, and pH is not adjusted before filtration. The vendor form explains feasibility is not actual continuous-machine performance.

  • Existing process context

    Appended rice-room process-control map RC-W-MP-4033, version 1.00, 15 July 2022, covers receiving/COA/inventory, magnet and mill prechecks, enzyme and yeast lot control, pressure-vessel rice cooking, fermentation, buffer/salt or 10% rice-vinegar adjustment, 1500-press flow/clarity/yield, bentonite/carbon and formulation, 800-press clarity/flow, pH adjustment, heat exchanger and storage. Operators, QA and maintenance are identified in the map; is not assigned authorship or execution of all controls.

  • Existing equipment context

    Appendix photographs record the sample container, wet press solids, existing 1500-press installation, and forklift/bin handling context. They are visual context for feasibility planning, not decanter installation or trial-completion proof.

  • Equipment quotation

    The dated 24 September 2024 proposal quotes DDP for the base C3E system with stand and controls; optional prices are solids handling, flush valves, centrate tank, NEMA 4X panel upgrade and feed pump/VFD/flowmeter integration. Elevation stand is included. The undated version retains option descriptions but omits prices. No purchase, installed cost or financial result is inferred.

  • Pilot objective

    Defined a pilot evaluation of product recovery, filter-press consumables, waste, water, electricity and operator labor before full-scale capital commitment.

  • Pilot planning

    Planned existing-utility use, temporary hose connections and vendor-supported onsite testing; completed vendor laboratory feasibility informed the pilot plan.

  • Pilot planning

    Developed a planned three-day decanter supplier rice-wine decanter trial using the existing 60 A circuit, existing feed pump and temporary connections; defined turbidity, solids-concentration and wine-loss testing before capital commitment.

  • Pilot planning

    Planned three-day onsite trial and three-to-four-week post-order mobilization; existing 60 A circuit; 250 gallons of 1% caustic at 140°F prepared in the existing filter-feed tank; modified tote for solids/waste collection; estimated 50-75% capital-cost advantage and four-to-five-times longer rebuild intervals versus separator-style alternatives.

  • Competency and project record

    Developed a planned three-day decanter supplier modular trial using the existing 60 A three-phase circuit and feed pump, temporary sanitary connections, and turbidity, solids-concentration and wine-loss measurements. The existing filter-feed tank prepares 250 gallons of 1% caustic at 140°F; a modified tote collects solids and drainage.

  • Sanitary and aseptic: Controlled case details

    Developed a low-disruption decanter supplier modular pilot using existing plant power and feed-pump infrastructure.

  • Sanitary and aseptic: Controlled case details

    Temporary sanitary product, CIP, and waste connections.

  • Sanitary and aseptic: Controlled case details

    Three-day active trial.

  • Sanitary and aseptic: Controlled case details

    Existing 60 A three-phase circuit.

  • Planned trial preparation

    Prepare 250 gallons of 1% caustic at 140°F in the existing filter-feed tank; use the modified tote for trial solids and drainage.

  • Sanitary and aseptic: Controlled case details

    1 percent caustic at 140 degrees F.

  • Sanitary and aseptic: Controlled case details

    Turbidity, solids-concentration, and wine-loss testing.

  • R&D supplement

    Developed a modular rice-wine decanter pilot using existing plant power and feed-pump infrastructure, temporary sanitary connections, planned turbidity/solids/wine-loss testing, and heated caustic prepared in the existing filter-feed tank. The modified tote collects solids and drainage.

All portfolio connections
All portfolio connections (30)
Related analysis and application artifacts

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗