TSK-000243 · Technical context

Chillers, Building Controls, Ozone Treatment and Power

Explore the capability, case, and equipment connections for this activity.

Conceptual engineering illustration: cooling heat transfer
Conceptual engineering visualization · AI generated

Activity Detail

Chillers, Building Controls, Ozone Treatment and Power

Case Context

Production-Cooling Upgrade with Three 160-Ton Chillers ↗

Project Context

PRJ-A-021 · Production-Cooling Upgrade with Three 160-Ton Chillers ↗

Capabilities

Systems & Equipment

All Portfolio Connections

All portfolio connections (14)

Project Ownership and Delivery Context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

modeled demand and the roughly 78-ton peak thermal deficit, coordinated pumps and recirculation, and developed chiller staging and runtime balancing. Operating visibility and process-load monitoring connected the three 160-ton production chillers with the way the plant used cooling capacity.

Related Analysis and Application Artifacts

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗