CASE-067 · Engineering case

Line 2 Pasteurizer Upgrades

Developed a pasteurizer and hot-water-set upgrade scope to address thermal stability, automation and compliance requirements.

Conceptual engineering visualization: Line 2 Pasteurizer Upgrades
Conceptual engineering visualization · AI generated

Why the Work Mattered

Purpose and Operating Need

Restore regulatory compliance and thermal stability with a rebuilt hot water set and automation upgrades.

Engineering Approach

Engineering Approach

Engineering scope: Bottling & Packaging Systems, CIP Automation.

Outcome & Engineering Context

Outcome and Context

The engineering study compared an 80-ft existing hold tube with a 171-ft required length at a 115 GPM design rate. Restoration of compliance and thermal stability was the project objective; final acceptance is not stated.

Workstream Results & Impact

Workstream Portfolio Rollup

28,095,000 USD

Production and Packaging Modernization

Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.

Measures & Operating Detail

Engineering scope and design basis

Project scope and individual work packages are presented separately; project totals are not additive to their component values.

1 detail rows; 900 K project-family value.

Actions, Methods & Controls

ACTIVITIES IN CONTEXT

Additional Technical Detail

Roles & contributions
  • Project Ownership

    Full lifecycle project ownership

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Workstream context
All portfolio connections
All portfolio connections (9)
Project ownership and delivery context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Reviewed hold-tube length, process flow and thermal-control requirements, translated those requirements into the upgrade scope, and coordinated production, quality and utility interfaces. The delivery approach connected the design basis with controls verification and operating readiness.

Related analysis and application artifacts