PRJ-B-007 · Food ingredients manufacturer

480 V Electrical Service and Power-Quality Modernization

Owned the full project lifecycle, connecting capital planning, engineering, procurement, construction and operating readiness.

Conceptual engineering illustration: electrical power quality
Conceptual engineering visualization · AI generated

The Operating Context

Operating Context

Deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, conduit, primary and secondary distribution infrastructure, testing, and documentation. Established a five-year underground-primary resilience plan for long-term capacity.

Purpose & Engineering Scope

Purpose and Scope

Business Purpose

Directed utility coordination, installation, energization, commissioning, and turnover for the 2,000 A, 480 V service; deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, and distribution infrastructure; and resolved critical brownout and load-imbalance conditions through utility corrective action.

Technical Scope

Electrical-service and power-quality modernization covering the 2,000 A, 480 V service, utility coordination, nine 2,500–3,750 kVA pad-mounted transformers with 480 V secondaries, switchgear, feeders, grounding, distribution, monitoring, energization and commissioning, with corrective action for brownout and load imbalance.

The Work & Its Outcomes

Work and Outcomes

Engineering Approach

  • Utility coordination, load studies, transformer/switchgear strategy and protective coordination.
  • Directed deployment of nine 2,500–3,750 kVA, 480 V-secondary pad-mounted transformers with distribution, grounding and testing.
  • Coordinated outage staging, energization, commissioning, power-quality monitoring and turnover.

Results, Targets & Design Context

  • Resolved critical brownout and load-imbalance conditions through utility corrective action.
  • Completed operating procedures and spare-capacity planning, with a five-year underground-primary resilience strategy.

Project Delivery & Execution

Capital Planning and Full Lifecycle Ownership

Owned the full project lifecycle, from capital planning through engineering, procurement, construction, commissioning and operating readiness.
Full lifecycle ownership
  • Project Ownership

    Full lifecycle project ownership

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Connected Activities

Design and Multidisciplinary Coordination

Construction Sequencing and Field Oversight

Connected Activities

AFE Development, Procurement and Bid Evaluation

Connected Activities

Project Controls and Governance

Connected Activities

Quality, Commissioning and Operating Readiness

Connected Activities

Conceptual engineering illustration: bottling integration

TSK-000719 · Action

Scope-to-Delivery Work-Package Coordination

480 V Electrical Service and Power-Quality Modernization

Recorded application
Conceptual engineering illustration: as built turnover

TSK-000721 · Action

Led the 2,000 A, 480 V Electrical-Service Modernization, Coordinating Utility and Plant Work Through Installation, Energization, Protection and Power-Quality Verification, Commissioning and Turnover

480 V Electrical Service and Power-Quality Modernization

Recorded application
Conceptual engineering illustration: as built turnover

TSK-000723 · Action

Requirements-to-Acceptance and Turnover Controls

480 V Electrical Service and Power-Quality Modernization

Recorded application
Recorded delivery responsibilities and activities

Owned capital planning and the full delivery lifecycle. The cards connect the applicable responsibilities with the recorded work.

Delivery Activities

Conceptual engineering illustration: as built turnover

Analytical Methods & Quantitative Decision Support

Financial and Capital Investment Analysis

Statistical Quality and Process Analytics

Optimization and Operations Research

Supply Chain and Inventory Analysis

Uncertainty, Reliability and Queueing

Production-Rate Driver Analysis

Quality Engineering and Structured Improvement

Engineering Option Studies and Operating Models

KPI Ownership and Performance Interpretation

Analytical Capability and Practical Application

Related methods and applications

Technical Systems Ownership

Industrial Automation, Controls and OT Networks

Instrumentation and Tank Measurement

Connected Activities

Electrical Power and Hazardous-Area Interfaces

Connected Activities

Conceptual engineering illustration: electrical power quality

TSK-000258 · Action

Designed and Supported 2,000A, 480V Electrical Service from Utility Pole and Transformer Through Switchgear, Feeders, Conduit, Panelboards, and Dedicated Equipment Circuits

2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

Recorded application
Conceptual engineering illustration: electrical power quality

TSK-000264 · Method

Coordinated Utility Service, Transformer, Switchgear, Feeders, Panels, Dedicated Circuits, Power-Quality Data, Utility Corrective Actions, and HMI/Data-Acquisition Deployment

2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

Recorded application
Conceptual engineering illustration: electrical infrastructure retrofit

TSK-000717 · Action

Electrical-Service Modernization Scope

480 V Electrical Service and Power-Quality Modernization

Recorded application
Conceptual engineering illustration: as built turnover

TSK-000721 · Action

Led the 2,000 A, 480 V Electrical-Service Modernization, Coordinating Utility and Plant Work Through Installation, Energization, Protection and Power-Quality Verification, Commissioning and Turnover

480 V Electrical Service and Power-Quality Modernization

Recorded application

Acetation, Fermentation and Process Support

Connected Activities

Additional technical detail
Explore 3 detail records
  • Competency and project record

    2,000 A, 480 V electrical service, protection, power quality, monitoring, spare capacity, outage coordination, procedures, and five-year load planning; Budget: $9,700,000. Energized and commissioned electrical-service modernization; transferred and closed.

  • Competency and project record

    Delivered electrical scope included utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, power-quality monitoring, commissioning, operating procedures, spare capacity, and turnover; Electrical service and distribution modernization; 2,000 A; 480 V; five-year load-balancing plan; operational turnover completed

  • Competency and project record

    Directed the electrical service expansion and power-quality modernization; deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, and distribution infrastructure; diagnosed critical brownout and load-imbalance conditions; and coordinated corrective action with the electric utility across two incoming primary feeder sets; $194,000 favorable variance

Project Activities

Conceptual engineering illustration: electrical power quality

TSK-000258 · Action

Designed and Supported 2,000A, 480V Electrical Service from Utility Pole and Transformer Through Switchgear, Feeders, Conduit, Panelboards, and Dedicated Equipment Circuits

2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

Conceptual engineering illustration: electrical power quality

TSK-000264 · Method

Coordinated Utility Service, Transformer, Switchgear, Feeders, Panels, Dedicated Circuits, Power-Quality Data, Utility Corrective Actions, and HMI/Data-Acquisition Deployment

2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

Conceptual engineering illustration: electrical infrastructure retrofit

TSK-000717 · Action

Electrical-Service Modernization Scope

480 V Electrical Service and Power-Quality Modernization

Conceptual engineering illustration: bottling integration

TSK-000719 · Action

Scope-to-Delivery Work-Package Coordination

480 V Electrical Service and Power-Quality Modernization

Conceptual engineering illustration: as built turnover

TSK-000721 · Action

Led the 2,000 A, 480 V Electrical-Service Modernization, Coordinating Utility and Plant Work Through Installation, Energization, Protection and Power-Quality Verification, Commissioning and Turnover

480 V Electrical Service and Power-Quality Modernization

Conceptual engineering illustration: as built turnover

TSK-000723 · Action

Requirements-to-Acceptance and Turnover Controls

480 V Electrical Service and Power-Quality Modernization

Project Measures

Workstream Portfolio Rollup

15,255,000 USD

Electrical Infrastructure Modernization

Portfolio value: 5,555,000 USD existing workstream scope plus 9,700,000 USD for the electrical service and power-quality project, counted once. Actual cost and estimate at completion are separate project measures.

Measure or outcomeValue or resultMeaning and operating scope
Portfolio Capital Value / Project Budget9,700,000 USDBudget basis; counted once in the electrical workstream portfolio rollup.
Actual Cost9,306,180 USDActual project cost recorded in the source portfolio.
Estimate at Completion9,506,000 USDForecast total project cost at completion.
Forecast Variance to Budget194,000 USDBudget less estimate at completion; forecast variance rather than final realized savings.
Electrical Service Current2,000 AEquipment Rating
Installed rating

Applies to: 480 V Electrical Service and Power-Quality Modernization

New electrical service — Installed, energized service rating.

Electrical Service Voltage480 VEquipment Rating
Installed rating

Applies to: 480 V Electrical Service and Power-Quality Modernization

New electrical service — Installed service voltage.

Resilience Planning Horizon5 yearsTarget
Planning horizon

Applies to: 480 V Electrical Service and Power-Quality Modernization

Underground primary-distribution resilience plan — Strategic underground-primary framework; separate from the completed transformer deployment.

Pad-Mounted Transformers Deployed9 transformersActual Result
Completed deployment quantity

Applies to: 480 V Electrical Service and Power-Quality Modernization

Electrical-service modernization — Nine deployed pad-mounted transformers with associated switchgear, grounding and distribution.

Transformer Rating2,500 to 3,750 kVAEquipment Rating
Installed rating range

Applies to: 480 V Electrical Service and Power-Quality Modernization

Nine pad-mounted transformers — Individual transformer service-point ratings; do not sum both range endpoints or multiply a single selected rating across all nine.

Incoming Primary Feeder Sets2 setsScope or Inventory Quantity
Utility interface quantity

Applies to: 480 V Electrical Service and Power-Quality Modernization

Power-quality corrective coordination — Two incoming pole-fed primary feeder sets were the utility-coordination context.

Recorded outcomeResolved critical brownout and load-imbalance conditions through utility corrective action.480 V Electrical Service and Power-Quality Modernization
Recorded outcomeCompleted operating procedures and spare-capacity planning, with a five-year underground-primary resilience strategy.480 V Electrical Service and Power-Quality Modernization

Explore the Case Studies

Portfolio Artifact Index

Project lifecycle documents
Explore 76 document purposes and project phases
  • PRJ-B-007-SE-F1-001

    Business Case and Opportunity Statement

    FEL 1 / Concept · Business and decision documents · 2016-01-12 · PRJ-B-007-WBS-F1-01 · PRJ-B-007-BL-F1-B01

    Establish the controlled business case and opportunity statement needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F1-002

    Project Charter and Initial Scope / Battery Limits

    FEL 1 / Concept · Business and decision documents · 2016-01-25 · PRJ-B-007-WBS-F1-02 · PRJ-B-007-BL-F1-B01

    Establish the controlled project charter and initial scope / battery limits needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F1-003

    Stakeholder Needs and Operating Context

    FEL 1 / Concept · Reports · 2016-02-07 · PRJ-B-007-WBS-F1-03 · PRJ-B-007-BL-F1-B01

    Establish the controlled stakeholder needs and operating context needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F1-004

    Concept Alternatives and Screening Study

    FEL 1 / Concept · Studies and analyses · 2016-02-20 · PRJ-B-007-WBS-F1-04 · PRJ-B-007-BL-F1-B01

    Establish the controlled concept alternatives and screening study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F1-005

    Preliminary Schedule and Class 5 Cost Estimate

    FEL 1 / Concept · Studies and analyses · 2016-03-04 · PRJ-B-007-WBS-F1-01 · PRJ-B-007-BL-F1-B01

    Establish the controlled preliminary schedule and class 5 cost estimate needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F1-006

    Initial Risk, Assumption, and Decision Register

    FEL 1 / Concept · Registers and indexes · 2016-03-17 · PRJ-B-007-WBS-F1-02 · PRJ-B-007-BL-F1-B01

    Establish the controlled initial risk, assumption, and decision register needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-001

    Option Study and Weighted Decision Analysis

    FEL 2 / Select · Studies and analyses · 2016-03-30 · PRJ-B-007-WBS-F2-01 · PRJ-B-007-BL-F2-B01

    Establish the controlled option study and weighted decision analysis needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-002

    Design Basis Memorandum

    FEL 2 / Select · Design definitions · 2016-04-13 · PRJ-B-007-WBS-F2-02 · PRJ-B-007-BL-F2-B01

    Establish the controlled design basis memorandum needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-003

    Site, Layout, and Process Alternative Study

    FEL 2 / Select · Studies and analyses · 2016-04-27 · PRJ-B-007-WBS-F2-03 · PRJ-B-007-BL-F2-B01

    Establish the controlled site, layout, and process alternative study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-004

    Stakeholder and System Requirements Specification

    FEL 2 / Select · Specifications · 2016-05-11 · PRJ-B-007-WBS-F2-04 · PRJ-B-007-BL-F2-B01

    Establish the controlled stakeholder and system requirements specification needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-005

    Concept Architecture and Interface Definition

    FEL 2 / Select · Design definitions · 2016-05-24 · PRJ-B-007-WBS-F2-01 · PRJ-B-007-BL-F2-B01

    Establish the controlled concept architecture and interface definition needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-006

    HAZID / Constructability / Operability Study

    FEL 2 / Select · Studies and analyses · 2016-06-07 · PRJ-B-007-WBS-F2-02 · PRJ-B-007-BL-F2-B01

    Establish the controlled hazid / constructability / operability study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-007

    Class 4 Estimate and Level 2 Schedule

    FEL 2 / Select · Studies and analyses · 2016-06-21 · PRJ-B-007-WBS-F2-03 · PRJ-B-007-BL-F2-B01

    Establish the controlled class 4 estimate and level 2 schedule needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F2-008

    Selected Concept and G2 Decision Dossier

    FEL 2 / Select · Dossiers and manual sets · 2016-07-05 · PRJ-B-007-WBS-F2-04 · PRJ-B-007-BL-F2-B01

    Establish the controlled selected concept and g2 decision dossier needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-001

    Defined Scope and Design Deliverables Register

    FEL 3 / Define · Registers and indexes · 2016-07-19 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01

    Establish the controlled defined scope and design deliverables register needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-002

    Baselined System Requirements Specification

    FEL 3 / Define · Specifications · 2016-08-02 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01

    Establish the controlled baselined system requirements specification needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-003

    System Architecture and Interface Control Document

    FEL 3 / Define · Design definitions · 2016-08-16 · PRJ-B-007-WBS-F3-03 · PRJ-B-007-BL-F3-B01

    Establish the controlled system architecture and interface control document needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-004

    Project Execution Plan

    FEL 3 / Define · Plans · 2016-08-30 · PRJ-B-007-WBS-F3-04 · PRJ-B-007-BL-F3-B01

    Establish the controlled project execution plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-005

    WBS, Work Package, and Responsibility Baseline

    FEL 3 / Define · Baselines and manifests · 2016-09-14 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01

    Establish the controlled wbs, work package, and responsibility baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-006

    Class 3 Estimate and Cost Baseline

    FEL 3 / Define · Baselines and manifests · 2016-09-28 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01

    Establish the controlled class 3 estimate and cost baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-007

    Coordinated Control Schedule and Resource Plan

    FEL 3 / Define · Plans · 2016-10-12 · PRJ-B-007-WBS-F3-03 · PRJ-B-007-BL-F3-B01

    Establish the controlled coordinated control schedule and resource plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-008

    Procurement and Contracting Plan

    FEL 3 / Define · Plans · 2016-10-26 · PRJ-B-007-WBS-F3-04 · PRJ-B-007-BL-F3-B01

    Establish the controlled procurement and contracting plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-009

    V&V, Acceptance, Commissioning, and Turnover Strategy

    FEL 3 / Define · Plans · 2016-11-09 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01

    Establish the controlled v&v, acceptance, commissioning, and turnover strategy needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-F3-010

    FID / G3 Approval and Baseline Manifest

    FEL 3 / Define · Certificates and approvals · 2016-11-24 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01

    Establish the controlled fid / g3 approval and baseline manifest needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-001

    Detailed Design Management Plan

    Detailed Design · Plans · 2016-12-08 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01

    Establish the controlled detailed design management plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-002

    Process / Functional Design Package

    Detailed Design · Design definitions · 2016-12-22 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01

    Establish the controlled process / functional design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-003

    Mechanical and Piping Design Package

    Detailed Design · Design definitions · 2017-01-05 · PRJ-B-007-WBS-DD-03 · PRJ-B-007-BL-DD-B01

    Establish the controlled mechanical and piping design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-004

    Electrical Power and Controls Design Package

    Detailed Design · Design definitions · 2017-01-19 · PRJ-B-007-WBS-DD-04 · PRJ-B-007-BL-DD-B01

    Establish the controlled electrical power and controls design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-005

    Civil, Structural, and Architectural Design Package

    Detailed Design · Design definitions · 2017-02-03 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01

    Establish the controlled civil, structural, and architectural design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-006

    Instrumentation, Automation, and Data Design Package

    Detailed Design · Design definitions · 2017-02-17 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01

    Establish the controlled instrumentation, automation, and data design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-007

    Safety, Reliability, and Maintainability Analysis

    Detailed Design · Studies and analyses · 2017-03-03 · PRJ-B-007-WBS-DD-03 · PRJ-B-007-BL-DD-B01

    Establish the controlled safety, reliability, and maintainability analysis needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-008

    Design Review and Comment Resolution Record

    Detailed Design · Records and logs · 2017-03-17 · PRJ-B-007-WBS-DD-04 · PRJ-B-007-BL-DD-B01

    Establish the controlled design review and comment resolution record needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-009

    Issued-for-Construction Design Baseline

    Detailed Design · Baselines and manifests · 2017-03-31 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01

    Establish the controlled issued-for-construction design baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-DD-010

    Design V&V Evidence Index

    Detailed Design · Registers and indexes · 2017-04-15 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01

    Establish the controlled design v&v evidence index needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-001

    Procurement Package and Bid List

    Procurement · Registers and indexes · 2017-04-29 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01

    Establish the controlled procurement package and bid list needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-002

    Technical Requisition and Datasheet Set

    Procurement · Specifications · 2017-05-14 · PRJ-B-007-WBS-PR-02 · PRJ-B-007-BL-PR-B01

    Establish the controlled technical requisition and datasheet set needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-003

    Commercial Bid Evaluation and Award Recommendation

    Procurement · Studies and analyses · 2017-05-29 · PRJ-B-007-WBS-PR-03 · PRJ-B-007-BL-PR-B01

    Establish the controlled commercial bid evaluation and award recommendation needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-004

    Technical Bid Evaluation and Clarification Log

    Procurement · Registers and indexes · 2017-06-12 · PRJ-B-007-WBS-PR-04 · PRJ-B-007-BL-PR-B01

    Establish the controlled technical bid evaluation and clarification log needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-005

    Purchase Order / Contract and Scope of Supply

    Procurement · Business and decision documents · 2017-06-27 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01

    Establish the controlled purchase order / contract and scope of supply needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-006

    Supplier Quality and Inspection Plan

    Procurement · Plans · 2017-07-12 · PRJ-B-007-WBS-PR-02 · PRJ-B-007-BL-PR-B01

    Establish the controlled supplier quality and inspection plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-007

    Vendor Data, Submittal, and RFI Register

    Procurement · Registers and indexes · 2017-07-26 · PRJ-B-007-WBS-PR-03 · PRJ-B-007-BL-PR-B01

    Establish the controlled vendor data, submittal, and rfi register needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-008

    Expediting and Logistics Plan

    Procurement · Plans · 2017-08-10 · PRJ-B-007-WBS-PR-04 · PRJ-B-007-BL-PR-B01

    Establish the controlled expediting and logistics plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-PR-009

    Factory Acceptance Test Procedure and Report

    Procurement · Procedures · 2017-08-25 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01

    Establish the controlled factory acceptance test procedure and report needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-001

    Construction / Fabrication Execution Plan

    Fabrication / Construction · Plans · 2017-09-15 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01

    Establish the controlled construction / fabrication execution plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-002

    Site Logistics, Safety, and Permit Plan

    Fabrication / Construction · Plans · 2017-10-07 · PRJ-B-007-WBS-FC-02 · PRJ-B-007-BL-FC-B01

    Establish the controlled site logistics, safety, and permit plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-003

    Fabrication Drawing and Shop Package

    Fabrication / Construction · Design definitions · 2017-10-29 · PRJ-B-007-WBS-FC-03 · PRJ-B-007-BL-FC-B01

    Establish the controlled fabrication drawing and shop package needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-004

    Field Work Package and Installation Method

    Fabrication / Construction · Procedures · 2017-11-20 · PRJ-B-007-WBS-FC-04 · PRJ-B-007-BL-FC-B01

    Establish the controlled field work package and installation method needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-005

    Inspection and Test Plan / Quality Records

    Fabrication / Construction · Plans · 2017-12-12 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01

    Establish the controlled inspection and test plan / quality records needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-006

    Daily Progress and Quantity Report

    Fabrication / Construction · Records and logs · 2018-01-03 · PRJ-B-007-WBS-FC-02 · PRJ-B-007-BL-FC-B01

    Establish the controlled daily progress and quantity report needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-007

    Nonconformity and Corrective Action Record

    Fabrication / Construction · Records and logs · 2018-01-25 · PRJ-B-007-WBS-FC-03 · PRJ-B-007-BL-FC-B01

    Establish the controlled nonconformity and corrective action record needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-008

    Redline Drawing and Field Change Register

    Fabrication / Construction · Registers and indexes · 2018-02-16 · PRJ-B-007-WBS-FC-04 · PRJ-B-007-BL-FC-B01

    Establish the controlled redline drawing and field change register needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-FC-009

    Mechanical Completion Certificate and Punch List

    Fabrication / Construction · Certificates and approvals · 2018-03-10 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01

    Establish the controlled mechanical completion certificate and punch list needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-001

    System Coordination and Interface Plan

    Installation and Interface Coordination · Plans · 2018-03-24 · PRJ-B-007-WBS-IN-01 · PRJ-B-007-BL-IN-B01

    Establish the controlled system coordination and interface plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-002

    Installation Completion and Walkdown Record

    Installation and Interface Coordination · Records and logs · 2018-04-07 · PRJ-B-007-WBS-IN-02 · PRJ-B-007-BL-IN-B01

    Establish the controlled installation completion and walkdown record needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-003

    Controls / Software Configuration Baseline

    Installation and Interface Coordination · Baselines and manifests · 2018-04-21 · PRJ-B-007-WBS-IN-03 · PRJ-B-007-BL-IN-B01

    Establish the controlled controls / software configuration baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-004

    Loop Check, Continuity, and Calibration Records

    Installation and Interface Coordination · Records and logs · 2018-05-05 · PRJ-B-007-WBS-IN-04 · PRJ-B-007-BL-IN-B01

    Establish the controlled loop check, continuity, and calibration records needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-005

    Cleaning, Flushing, and Pre-Operational Test Record

    Installation and Interface Coordination · Procedures · 2018-05-19 · PRJ-B-007-WBS-IN-01 · PRJ-B-007-BL-IN-B01

    Establish the controlled cleaning, flushing, and pre-operational test record needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-006

    System Completion Dossier

    Installation and Interface Coordination · Dossiers and manual sets · 2018-06-02 · PRJ-B-007-WBS-IN-02 · PRJ-B-007-BL-IN-B01

    Establish the controlled system completion dossier needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-IN-007

    Ready-for-Commissioning Certificate

    Installation and Interface Coordination · Certificates and approvals · 2018-06-17 · PRJ-B-007-WBS-IN-03 · PRJ-B-007-BL-IN-B01

    Establish the controlled ready-for-commissioning certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-001

    Commissioning and Startup Plan

    Commissioning / Startup · Plans · 2018-06-30 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01

    Establish the controlled commissioning and startup plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-002

    Pre-Startup Safety / Operational Readiness Review

    Commissioning / Startup · Reports · 2018-07-13 · PRJ-B-007-WBS-CS-02 · PRJ-B-007-BL-CS-B01

    Establish the controlled pre-startup safety / operational readiness review needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-003

    Commissioning Procedure and Results

    Commissioning / Startup · Procedures · 2018-07-27 · PRJ-B-007-WBS-CS-03 · PRJ-B-007-BL-CS-B01

    Establish the controlled commissioning procedure and results needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-004

    Startup and Ramp-Up Log

    Commissioning / Startup · Registers and indexes · 2018-08-09 · PRJ-B-007-WBS-CS-04 · PRJ-B-007-BL-CS-B01

    Establish the controlled startup and ramp-up log needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-005

    Performance Guarantee and Capacity Test Report

    Commissioning / Startup · Studies and analyses · 2018-08-23 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01

    Establish the controlled performance guarantee and capacity test report needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-006

    Reliability Demonstration Run Report

    Commissioning / Startup · Studies and analyses · 2018-09-05 · PRJ-B-007-WBS-CS-02 · PRJ-B-007-BL-CS-B01

    Establish the controlled reliability demonstration run report needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-007

    Operator and Maintainer Training Record

    Commissioning / Startup · Records and logs · 2018-09-19 · PRJ-B-007-WBS-CS-03 · PRJ-B-007-BL-CS-B01

    Establish the controlled operator and maintainer training record needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-008

    Commissioning Anomaly and Punch Closure Register

    Commissioning / Startup · Registers and indexes · 2018-10-02 · PRJ-B-007-WBS-CS-04 · PRJ-B-007-BL-CS-B01

    Establish the controlled commissioning anomaly and punch closure register needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-CS-009

    Performance Acceptance Certificate

    Commissioning / Startup · Certificates and approvals · 2018-10-16 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01

    Establish the controlled performance acceptance certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-001

    As-Built / as-Configured Baseline Manifest

    Operational Turnover / Closeout · Baselines and manifests · 2018-10-25 · PRJ-B-007-WBS-OT-01 · PRJ-B-007-BL-OT-B01

    Establish the controlled as-built / as-configured baseline manifest needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-002

    Operations and Maintenance Manual Set

    Operational Turnover / Closeout · Dossiers and manual sets · 2018-11-04 · PRJ-B-007-WBS-OT-02 · PRJ-B-007-BL-OT-B01

    Establish the controlled operations and maintenance manual set needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-003

    Asset, Spare Parts, and Warranty Register

    Operational Turnover / Closeout · Registers and indexes · 2018-11-13 · PRJ-B-007-WBS-OT-03 · PRJ-B-007-BL-OT-B01

    Establish the controlled asset, spare parts, and warranty register needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-004

    Final Technical and Commercial Acceptance Certificate

    Operational Turnover / Closeout · Certificates and approvals · 2018-11-23 · PRJ-B-007-WBS-OT-04 · PRJ-B-007-BL-OT-B01

    Establish the controlled final technical and commercial acceptance certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-005

    Operational Turnover Dossier and Ownership Transfer

    Operational Turnover / Closeout · Dossiers and manual sets · 2018-12-02 · PRJ-B-007-WBS-OT-01 · PRJ-B-007-BL-OT-B01

    Establish the controlled operational turnover dossier and ownership transfer needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-006

    Final Cost, Schedule, Contract, and Claims Closeout

    Operational Turnover / Closeout · Studies and analyses · 2018-12-12 · PRJ-B-007-WBS-OT-02 · PRJ-B-007-BL-OT-B01

    Establish the controlled final cost, schedule, contract, and claims closeout needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-007

    Controlled Records Archive and Retrieval Index

    Operational Turnover / Closeout · Registers and indexes · 2018-12-21 · PRJ-B-007-WBS-OT-03 · PRJ-B-007-BL-OT-B01

    Establish the controlled controlled records archive and retrieval index needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

  • PRJ-B-007-SE-OT-008

    Lessons Learned and Benefit Realization Baseline

    Operational Turnover / Closeout · Baselines and manifests · 2018-12-31 · PRJ-B-007-WBS-OT-04 · PRJ-B-007-BL-OT-B01

    Establish the controlled lessons learned and benefit realization baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.

Related analysis and application artifacts
Show 4 more connections
All portfolio connections
All portfolio connections (92)
Connected collections

Workstream & Initiative

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗