Capital Strategy and Business Alignment
Translate Growth Forecasts, Customer Demand, Operating Constraints, and Asset Condition into Capital Priorities
Engineering practice and documented application
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPPRJ-B-007 · Food ingredients manufacturer
Owned the full project lifecycle, connecting capital planning, engineering, procurement, construction and operating readiness.

Workstream: Electrical Infrastructure Modernization
Deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, conduit, primary and secondary distribution infrastructure, testing, and documentation. Established a five-year underground-primary resilience plan for long-term capacity.
Directed utility coordination, installation, energization, commissioning, and turnover for the 2,000 A, 480 V service; deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, and distribution infrastructure; and resolved critical brownout and load-imbalance conditions through utility corrective action.
Electrical-service and power-quality modernization covering the 2,000 A, 480 V service, utility coordination, nine 2,500–3,750 kVA pad-mounted transformers with 480 V secondaries, switchgear, feeders, grounding, distribution, monitoring, energization and commissioning, with corrective action for brownout and load imbalance.
Full lifecycle project ownership
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Capital Strategy and Business Alignment
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

TSK-000714 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000723 · Action
480 V Electrical Service and Power-Quality Modernization

Action
Applies capabilities

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

TSK-000715 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000949 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

TSK-000715 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000719 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000951 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
AFE and Capital-Governance Controls
Engineering practice and documented application

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

TSK-000719 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000723 · Action
480 V Electrical Service and Power-Quality Modernization

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

TSK-000715 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000723 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000951 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

TSK-000719 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000721 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000723 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000734 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000951 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded applicationOwned capital planning and the full delivery lifecycle. The cards connect the applicable responsibilities with the recorded work.

Capital Strategy and Business Alignment
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Project Lifecycle, FEL, and Execution Models
Engineering practice and documented application

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

Workstream, Portfolio, and Stakeholder Leadership
Engineering practice and documented application

AFE and Capital-Governance Controls
Engineering practice and documented application

Estimating, Financial Control, and Expense Traceability
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Scheduling, Shutdowns, and Execution Sequencing
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Procurement, Contracts, and Supplier Coordination
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Commissioning, Qualification, Acceptance, and Turnover
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Lifecycle Artifacts: Procurement and Construction
Engineering practice and documented application

Action
Applies capabilities






Action
Applies capabilities

Action
Applies capabilities


Investment Economics and Lifecycle Analysis
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Risk, Uncertainty, and Decision Support
Engineering practice and documented application

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Statistical Quality, Measurement Systems, and Sampling
Academic preparation and analytical method

Optimization and Operations Research
Academic preparation and analytical method

Optimization and Operations Research
Engineering practice and documented application

Forecasting, Inventory, Supply Chain, and Logistics
Academic preparation and analytical method

Forecasting, Inventory, Supply Chain, and Logistics
Academic preparation and analytical method

Stochastic Models and Uncertainty Analytics
Academic preparation and analytical method

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Lean Six Sigma, Quality Systems, and Governance Maturity
Engineering practice and documented application

Investment Economics and Lifecycle Analysis
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

Optimization and Operations Research
Academic preparation and analytical method

Optimization and Operations Research
Engineering practice and documented application

Data Analytics, BI, and Operational Reporting
Engineering practice and documented application

PLC, HMI, SCADA, Drives, and Process Automation
Engineering practice and documented application

TSK-000263 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000264 · Method
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

Instrumentation, Measurement, and Standards
Engineering practice and documented application

TSK-000733 · Control requirements
480 V Electrical Service and Power-Quality Modernization

Electrical Utility Service, Power Quality, and Resilience
Engineering practice and documented application

Electrical Utility Service, Power Quality, and Resilience
Engineering practice and documented application

Electrical Utility Service, Power Quality, and Resilience
Engineering practice and documented application

Electrical Utility Service, Power Quality, and Resilience
Engineering practice and documented application

Electrical Utility Service, Power Quality, and Resilience
Engineering practice and documented application

Electrical Distribution Design and Installation Packages
Engineering practice and documented application

Electrical Distribution Design and Installation Packages
Engineering practice and documented application

Electrical Distribution Design and Installation Packages
Engineering practice and documented application

Electrical Testing, Standby Power, and Energization
Engineering practice and documented application

Electrical Testing, Standby Power, and Energization
Engineering practice and documented application

Electrical Testing, Standby Power, and Energization
Engineering practice and documented application

Hazardous Locations, Machine Safety, and Heat Trace
Engineering practice and documented application

Hazardous Locations, Machine Safety, and Heat Trace
Engineering practice and documented application

TSK-000258 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000259 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000260 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000261 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000262 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000264 · Method
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000717 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000721 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000725 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000726 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000727 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000731 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000732 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000737 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000949 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
TSK-000950 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
TSK-000951 · Action
480 V Electrical Service and Power-Quality Modernization
Recorded application
Hygienic Design, Sanitary Systems, and Aseptic Bulk Handling
Engineering practice and documented application

TSK-000728 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000729 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000730 · Control requirements
480 V Electrical Service and Power-Quality Modernization
2,000 A, 480 V electrical service, protection, power quality, monitoring, spare capacity, outage coordination, procedures, and five-year load planning; Budget: $9,700,000. Energized and commissioned electrical-service modernization; transferred and closed.
Delivered electrical scope included utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, power-quality monitoring, commissioning, operating procedures, spare capacity, and turnover; Electrical service and distribution modernization; 2,000 A; 480 V; five-year load-balancing plan; operational turnover completed
Directed the electrical service expansion and power-quality modernization; deployed nine 2,500 to 3,750 kVA, 480 V-secondary pad-mounted transformers with associated switchgear, grounding, and distribution infrastructure; diagnosed critical brownout and load-imbalance conditions; and coordinated corrective action with the electric utility across two incoming primary feeder sets; $194,000 favorable variance

TSK-000258 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000259 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000260 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000261 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000262 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000263 · Action
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000264 · Method
2,000 A Electrical-Service Expansion and Power-Quality Diagnosis

TSK-000714 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000715 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000717 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000719 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000721 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000723 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000725 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000726 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000727 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000728 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000729 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000730 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000731 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000732 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000733 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000734 · Control requirements
480 V Electrical Service and Power-Quality Modernization

TSK-000737 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000949 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000950 · Action
480 V Electrical Service and Power-Quality Modernization

TSK-000951 · Action
480 V Electrical Service and Power-Quality Modernization
Workstream Portfolio Rollup
15,255,000 USD
Electrical Infrastructure Modernization
Portfolio value: 5,555,000 USD existing workstream scope plus 9,700,000 USD for the electrical service and power-quality project, counted once. Actual cost and estimate at completion are separate project measures.
| Measure or outcome | Value or result | Meaning and operating scope |
|---|---|---|
| Portfolio Capital Value / Project Budget | 9,700,000 USD | Budget basis; counted once in the electrical workstream portfolio rollup. |
| Actual Cost | 9,306,180 USD | Actual project cost recorded in the source portfolio. |
| Estimate at Completion | 9,506,000 USD | Forecast total project cost at completion. |
| Forecast Variance to Budget | 194,000 USD | Budget less estimate at completion; forecast variance rather than final realized savings. |
| Electrical Service Current | 2,000 A | Equipment Rating Installed rating Applies to: 480 V Electrical Service and Power-Quality Modernization New electrical service — Installed, energized service rating. |
| Electrical Service Voltage | 480 V | Equipment Rating Installed rating Applies to: 480 V Electrical Service and Power-Quality Modernization New electrical service — Installed service voltage. |
| Resilience Planning Horizon | 5 years | Target Planning horizon Applies to: 480 V Electrical Service and Power-Quality Modernization Underground primary-distribution resilience plan — Strategic underground-primary framework; separate from the completed transformer deployment. |
| Pad-Mounted Transformers Deployed | 9 transformers | Actual Result Completed deployment quantity Applies to: 480 V Electrical Service and Power-Quality Modernization Electrical-service modernization — Nine deployed pad-mounted transformers with associated switchgear, grounding and distribution. |
| Transformer Rating | 2,500 to 3,750 kVA | Equipment Rating Installed rating range Applies to: 480 V Electrical Service and Power-Quality Modernization Nine pad-mounted transformers — Individual transformer service-point ratings; do not sum both range endpoints or multiply a single selected rating across all nine. |
| Incoming Primary Feeder Sets | 2 sets | Scope or Inventory Quantity Utility interface quantity Applies to: 480 V Electrical Service and Power-Quality Modernization Power-quality corrective coordination — Two incoming pole-fed primary feeder sets were the utility-coordination context. |
| Recorded outcome | Resolved critical brownout and load-imbalance conditions through utility corrective action. | 480 V Electrical Service and Power-Quality Modernization |
| Recorded outcome | Completed operating procedures and spare-capacity planning, with a five-year underground-primary resilience strategy. | 480 V Electrical Service and Power-Quality Modernization |
CASE-106 · Engineering case
Led electrical service expansion and power-quality improvement to support new manufacturing process capacity.
Read the Case ↗CASE-144 · Engineering case
Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
Read the Case ↗PRJ-B-007-SE-F1-001
FEL 1 / Concept · Business and decision documents · 2016-01-12 · PRJ-B-007-WBS-F1-01 · PRJ-B-007-BL-F1-B01
Establish the controlled business case and opportunity statement needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F1-002
FEL 1 / Concept · Business and decision documents · 2016-01-25 · PRJ-B-007-WBS-F1-02 · PRJ-B-007-BL-F1-B01
Establish the controlled project charter and initial scope / battery limits needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F1-003
FEL 1 / Concept · Reports · 2016-02-07 · PRJ-B-007-WBS-F1-03 · PRJ-B-007-BL-F1-B01
Establish the controlled stakeholder needs and operating context needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F1-004
FEL 1 / Concept · Studies and analyses · 2016-02-20 · PRJ-B-007-WBS-F1-04 · PRJ-B-007-BL-F1-B01
Establish the controlled concept alternatives and screening study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F1-005
FEL 1 / Concept · Studies and analyses · 2016-03-04 · PRJ-B-007-WBS-F1-01 · PRJ-B-007-BL-F1-B01
Establish the controlled preliminary schedule and class 5 cost estimate needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F1-006
FEL 1 / Concept · Registers and indexes · 2016-03-17 · PRJ-B-007-WBS-F1-02 · PRJ-B-007-BL-F1-B01
Establish the controlled initial risk, assumption, and decision register needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 1 / Concept. The record supports G1 Opportunity Authorization and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-001
FEL 2 / Select · Studies and analyses · 2016-03-30 · PRJ-B-007-WBS-F2-01 · PRJ-B-007-BL-F2-B01
Establish the controlled option study and weighted decision analysis needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-002
FEL 2 / Select · Design definitions · 2016-04-13 · PRJ-B-007-WBS-F2-02 · PRJ-B-007-BL-F2-B01
Establish the controlled design basis memorandum needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-003
FEL 2 / Select · Studies and analyses · 2016-04-27 · PRJ-B-007-WBS-F2-03 · PRJ-B-007-BL-F2-B01
Establish the controlled site, layout, and process alternative study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-004
FEL 2 / Select · Specifications · 2016-05-11 · PRJ-B-007-WBS-F2-04 · PRJ-B-007-BL-F2-B01
Establish the controlled stakeholder and system requirements specification needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-005
FEL 2 / Select · Design definitions · 2016-05-24 · PRJ-B-007-WBS-F2-01 · PRJ-B-007-BL-F2-B01
Establish the controlled concept architecture and interface definition needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-006
FEL 2 / Select · Studies and analyses · 2016-06-07 · PRJ-B-007-WBS-F2-02 · PRJ-B-007-BL-F2-B01
Establish the controlled hazid / constructability / operability study needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-007
FEL 2 / Select · Studies and analyses · 2016-06-21 · PRJ-B-007-WBS-F2-03 · PRJ-B-007-BL-F2-B01
Establish the controlled class 4 estimate and level 2 schedule needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F2-008
FEL 2 / Select · Dossiers and manual sets · 2016-07-05 · PRJ-B-007-WBS-F2-04 · PRJ-B-007-BL-F2-B01
Establish the controlled selected concept and g2 decision dossier needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 2 / Select. The record supports G2 Concept Selection and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-001
FEL 3 / Define · Registers and indexes · 2016-07-19 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01
Establish the controlled defined scope and design deliverables register needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-002
FEL 3 / Define · Specifications · 2016-08-02 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01
Establish the controlled baselined system requirements specification needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-003
FEL 3 / Define · Design definitions · 2016-08-16 · PRJ-B-007-WBS-F3-03 · PRJ-B-007-BL-F3-B01
Establish the controlled system architecture and interface control document needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-004
FEL 3 / Define · Plans · 2016-08-30 · PRJ-B-007-WBS-F3-04 · PRJ-B-007-BL-F3-B01
Establish the controlled project execution plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-005
FEL 3 / Define · Baselines and manifests · 2016-09-14 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01
Establish the controlled wbs, work package, and responsibility baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-006
FEL 3 / Define · Baselines and manifests · 2016-09-28 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01
Establish the controlled class 3 estimate and cost baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-007
FEL 3 / Define · Plans · 2016-10-12 · PRJ-B-007-WBS-F3-03 · PRJ-B-007-BL-F3-B01
Establish the controlled coordinated control schedule and resource plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-008
FEL 3 / Define · Plans · 2016-10-26 · PRJ-B-007-WBS-F3-04 · PRJ-B-007-BL-F3-B01
Establish the controlled procurement and contracting plan needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-009
FEL 3 / Define · Plans · 2016-11-09 · PRJ-B-007-WBS-F3-01 · PRJ-B-007-BL-F3-B01
Establish the controlled v&v, acceptance, commissioning, and turnover strategy needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-F3-010
FEL 3 / Define · Certificates and approvals · 2016-11-24 · PRJ-B-007-WBS-F3-02 · PRJ-B-007-BL-F3-B01
Establish the controlled fid / g3 approval and baseline manifest needed to execute 480 V Electrical Service and Power-Quality Modernization during FEL 3 / Define. The record supports G3 Final Investment Decision and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-001
Detailed Design · Plans · 2016-12-08 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01
Establish the controlled detailed design management plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-002
Detailed Design · Design definitions · 2016-12-22 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01
Establish the controlled process / functional design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-003
Detailed Design · Design definitions · 2017-01-05 · PRJ-B-007-WBS-DD-03 · PRJ-B-007-BL-DD-B01
Establish the controlled mechanical and piping design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-004
Detailed Design · Design definitions · 2017-01-19 · PRJ-B-007-WBS-DD-04 · PRJ-B-007-BL-DD-B01
Establish the controlled electrical power and controls design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-005
Detailed Design · Design definitions · 2017-02-03 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01
Establish the controlled civil, structural, and architectural design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-006
Detailed Design · Design definitions · 2017-02-17 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01
Establish the controlled instrumentation, automation, and data design package needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-007
Detailed Design · Studies and analyses · 2017-03-03 · PRJ-B-007-WBS-DD-03 · PRJ-B-007-BL-DD-B01
Establish the controlled safety, reliability, and maintainability analysis needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-008
Detailed Design · Records and logs · 2017-03-17 · PRJ-B-007-WBS-DD-04 · PRJ-B-007-BL-DD-B01
Establish the controlled design review and comment resolution record needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-009
Detailed Design · Baselines and manifests · 2017-03-31 · PRJ-B-007-WBS-DD-01 · PRJ-B-007-BL-DD-B01
Establish the controlled issued-for-construction design baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-DD-010
Detailed Design · Registers and indexes · 2017-04-15 · PRJ-B-007-WBS-DD-02 · PRJ-B-007-BL-DD-B01
Establish the controlled design v&v evidence index needed to execute 480 V Electrical Service and Power-Quality Modernization during Detailed Design. The record supports G4 Design Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-001
Procurement · Registers and indexes · 2017-04-29 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01
Establish the controlled procurement package and bid list needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-002
Procurement · Specifications · 2017-05-14 · PRJ-B-007-WBS-PR-02 · PRJ-B-007-BL-PR-B01
Establish the controlled technical requisition and datasheet set needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-003
Procurement · Studies and analyses · 2017-05-29 · PRJ-B-007-WBS-PR-03 · PRJ-B-007-BL-PR-B01
Establish the controlled commercial bid evaluation and award recommendation needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-004
Procurement · Registers and indexes · 2017-06-12 · PRJ-B-007-WBS-PR-04 · PRJ-B-007-BL-PR-B01
Establish the controlled technical bid evaluation and clarification log needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-005
Procurement · Business and decision documents · 2017-06-27 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01
Establish the controlled purchase order / contract and scope of supply needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-006
Procurement · Plans · 2017-07-12 · PRJ-B-007-WBS-PR-02 · PRJ-B-007-BL-PR-B01
Establish the controlled supplier quality and inspection plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-007
Procurement · Registers and indexes · 2017-07-26 · PRJ-B-007-WBS-PR-03 · PRJ-B-007-BL-PR-B01
Establish the controlled vendor data, submittal, and rfi register needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-008
Procurement · Plans · 2017-08-10 · PRJ-B-007-WBS-PR-04 · PRJ-B-007-BL-PR-B01
Establish the controlled expediting and logistics plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-PR-009
Procurement · Procedures · 2017-08-25 · PRJ-B-007-WBS-PR-01 · PRJ-B-007-BL-PR-B01
Establish the controlled factory acceptance test procedure and report needed to execute 480 V Electrical Service and Power-Quality Modernization during Procurement. The record supports G5 Procurement Release and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-001
Fabrication / Construction · Plans · 2017-09-15 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01
Establish the controlled construction / fabrication execution plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-002
Fabrication / Construction · Plans · 2017-10-07 · PRJ-B-007-WBS-FC-02 · PRJ-B-007-BL-FC-B01
Establish the controlled site logistics, safety, and permit plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-003
Fabrication / Construction · Design definitions · 2017-10-29 · PRJ-B-007-WBS-FC-03 · PRJ-B-007-BL-FC-B01
Establish the controlled fabrication drawing and shop package needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-004
Fabrication / Construction · Procedures · 2017-11-20 · PRJ-B-007-WBS-FC-04 · PRJ-B-007-BL-FC-B01
Establish the controlled field work package and installation method needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-005
Fabrication / Construction · Plans · 2017-12-12 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01
Establish the controlled inspection and test plan / quality records needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-006
Fabrication / Construction · Records and logs · 2018-01-03 · PRJ-B-007-WBS-FC-02 · PRJ-B-007-BL-FC-B01
Establish the controlled daily progress and quantity report needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-007
Fabrication / Construction · Records and logs · 2018-01-25 · PRJ-B-007-WBS-FC-03 · PRJ-B-007-BL-FC-B01
Establish the controlled nonconformity and corrective action record needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-008
Fabrication / Construction · Registers and indexes · 2018-02-16 · PRJ-B-007-WBS-FC-04 · PRJ-B-007-BL-FC-B01
Establish the controlled redline drawing and field change register needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-FC-009
Fabrication / Construction · Certificates and approvals · 2018-03-10 · PRJ-B-007-WBS-FC-01 · PRJ-B-007-BL-FC-B01
Establish the controlled mechanical completion certificate and punch list needed to execute 480 V Electrical Service and Power-Quality Modernization during Fabrication / Construction. The record supports G6 Mechanical Completion and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-001
Installation and Interface Coordination · Plans · 2018-03-24 · PRJ-B-007-WBS-IN-01 · PRJ-B-007-BL-IN-B01
Establish the controlled system coordination and interface plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-002
Installation and Interface Coordination · Records and logs · 2018-04-07 · PRJ-B-007-WBS-IN-02 · PRJ-B-007-BL-IN-B01
Establish the controlled installation completion and walkdown record needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-003
Installation and Interface Coordination · Baselines and manifests · 2018-04-21 · PRJ-B-007-WBS-IN-03 · PRJ-B-007-BL-IN-B01
Establish the controlled controls / software configuration baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-004
Installation and Interface Coordination · Records and logs · 2018-05-05 · PRJ-B-007-WBS-IN-04 · PRJ-B-007-BL-IN-B01
Establish the controlled loop check, continuity, and calibration records needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-005
Installation and Interface Coordination · Procedures · 2018-05-19 · PRJ-B-007-WBS-IN-01 · PRJ-B-007-BL-IN-B01
Establish the controlled cleaning, flushing, and pre-operational test record needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-006
Installation and Interface Coordination · Dossiers and manual sets · 2018-06-02 · PRJ-B-007-WBS-IN-02 · PRJ-B-007-BL-IN-B01
Establish the controlled system completion dossier needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-IN-007
Installation and Interface Coordination · Certificates and approvals · 2018-06-17 · PRJ-B-007-WBS-IN-03 · PRJ-B-007-BL-IN-B01
Establish the controlled ready-for-commissioning certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Installation / coordination. The record supports G7 Ready for Commissioning and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-001
Commissioning / Startup · Plans · 2018-06-30 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01
Establish the controlled commissioning and startup plan needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-002
Commissioning / Startup · Reports · 2018-07-13 · PRJ-B-007-WBS-CS-02 · PRJ-B-007-BL-CS-B01
Establish the controlled pre-startup safety / operational readiness review needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-003
Commissioning / Startup · Procedures · 2018-07-27 · PRJ-B-007-WBS-CS-03 · PRJ-B-007-BL-CS-B01
Establish the controlled commissioning procedure and results needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-004
Commissioning / Startup · Registers and indexes · 2018-08-09 · PRJ-B-007-WBS-CS-04 · PRJ-B-007-BL-CS-B01
Establish the controlled startup and ramp-up log needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-005
Commissioning / Startup · Studies and analyses · 2018-08-23 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01
Establish the controlled performance guarantee and capacity test report needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-006
Commissioning / Startup · Studies and analyses · 2018-09-05 · PRJ-B-007-WBS-CS-02 · PRJ-B-007-BL-CS-B01
Establish the controlled reliability demonstration run report needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-007
Commissioning / Startup · Records and logs · 2018-09-19 · PRJ-B-007-WBS-CS-03 · PRJ-B-007-BL-CS-B01
Establish the controlled operator and maintainer training record needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-008
Commissioning / Startup · Registers and indexes · 2018-10-02 · PRJ-B-007-WBS-CS-04 · PRJ-B-007-BL-CS-B01
Establish the controlled commissioning anomaly and punch closure register needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-CS-009
Commissioning / Startup · Certificates and approvals · 2018-10-16 · PRJ-B-007-WBS-CS-01 · PRJ-B-007-BL-CS-B01
Establish the controlled performance acceptance certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Commissioning / Startup. The record supports G8 Performance Acceptance and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-001
Operational Turnover / Closeout · Baselines and manifests · 2018-10-25 · PRJ-B-007-WBS-OT-01 · PRJ-B-007-BL-OT-B01
Establish the controlled as-built / as-configured baseline manifest needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-002
Operational Turnover / Closeout · Dossiers and manual sets · 2018-11-04 · PRJ-B-007-WBS-OT-02 · PRJ-B-007-BL-OT-B01
Establish the controlled operations and maintenance manual set needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-003
Operational Turnover / Closeout · Registers and indexes · 2018-11-13 · PRJ-B-007-WBS-OT-03 · PRJ-B-007-BL-OT-B01
Establish the controlled asset, spare parts, and warranty register needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-004
Operational Turnover / Closeout · Certificates and approvals · 2018-11-23 · PRJ-B-007-WBS-OT-04 · PRJ-B-007-BL-OT-B01
Establish the controlled final technical and commercial acceptance certificate needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-005
Operational Turnover / Closeout · Dossiers and manual sets · 2018-12-02 · PRJ-B-007-WBS-OT-01 · PRJ-B-007-BL-OT-B01
Establish the controlled operational turnover dossier and ownership transfer needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-006
Operational Turnover / Closeout · Studies and analyses · 2018-12-12 · PRJ-B-007-WBS-OT-02 · PRJ-B-007-BL-OT-B01
Establish the controlled final cost, schedule, contract, and claims closeout needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-007
Operational Turnover / Closeout · Registers and indexes · 2018-12-21 · PRJ-B-007-WBS-OT-03 · PRJ-B-007-BL-OT-B01
Establish the controlled controlled records archive and retrieval index needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.
PRJ-B-007-SE-OT-008
Operational Turnover / Closeout · Baselines and manifests · 2018-12-31 · PRJ-B-007-WBS-OT-04 · PRJ-B-007-BL-OT-B01
Establish the controlled lessons learned and benefit realization baseline needed to execute 480 V Electrical Service and Power-Quality Modernization during Operational Turnover / Closeout. The record supports G9 Operational Turnover and Closeout and preserves the approved decision, execution, verification, acceptance, and configuration evidence used by successor work. This document applies to Electrical service and distribution modernization within PRJ-B-007 - 480 V Electrical Service and Power-Quality Modernization. The project scope is: Utility coordination, load study, transformer and switchgear strategy, feeders, conduit, panelboards, protective coordination, outage planning, installation, energization, monitoring, commissioning, and turnover. Energized 2,000 A, 480 V service with verified protection, power quality, spare capacity, operating procedures, and five-year load plan.