CASE-115 · Engineering case

Fiberoptic OT Network Phase 1 and Phase 2 Execution

Executed phased OT fiber modernization with cost-controlled AFE delivery, vendor selection, construction readiness, and live migration validation.

Conceptual engineering visualization: Fiberoptic OT Network Phase 1 and Phase 2 Execution
Conceptual engineering visualization · AI generated

Why the Work Mattered

Purpose and Operating Need

The OT network work required contractor qualification, equipment backorder sequencing, panel readiness, live IP migration, switch programming, and IT/controls validation in addition to network design.

Engineering Approach

Engineering Approach

The phased execution scope retained the existing architecture and included Phase 1, Phase 2, an equipment distributor and three network-equipment suppliers, 13 UPS units, 10 Gbps east-west backbone, armored OM3 fiber contractor qualification, drawing approvals, panel power-up, electrical feeds, fiber pulls, switch programming, equipment specifications, BOM breakdown, IP migration, lab/live validation, and remodel-aware final switch placement.

Outcome & Engineering Context

Outcome and Context

Improved OT resiliency, migration readiness, and implementation control within a phased workstream that retained future commissioning work.

Workstream Results & Impact

Workstream Portfolio Rollup

4,942,000 USD

OT Network and Controls Transformation

Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.

Measures & Operating Detail

MeasureValueType & meaningAttribution & operating context
East-West OT Backbone Data Rate10 GbpsEquipment Rating
Network architecture capacity

Applies to: Fiberoptic OT Network Phase 1 and Phase 2, Configuration and Cutover Execution

10 Gbps backbone

Engineering scope and design basis

Improved controls-network resiliency and reduced power-sag communication risk within implemented portions of the phased OT work. The design addressed bandwidth bottlenecks and placed switches to reduce future stranded-infrastructure risk; remaining commissioning was recorded separately.

Defined phased OT-network scope with Phase 1, Phase 2, an equipment distributor and three network-equipment suppliers, 13 UPS units, 10 Gbps east-west backbone, armored OM3 fiber contractor qualification, drawing approvals, panel power-up, electrical feeds, fiber pulls, switch programming, equipment specifications, BOM breakdown, IP migration, lab/live validation, and remodel-aware final switch placement.

Improved OT network implementation readiness, measured by Phase 1, Phase 2, 13 UPS units, 10 Gbps east-west backbone, by coordinating vendor procurement, drawings, panels, switch programming, electrical feeds, and fiber installation.

Phase 1; Phase 2; 13 UPS units; 10 Gbps backbone.

Prepared an AI-assisted configuration review and an undeployed staging baseline: For LAL-23

Prepared an AI-assisted configuration review and an undeployed staging baseline: AI aligned physical observations with switch configuration

Prepared an AI-assisted configuration review and an undeployed staging baseline: identified shutdown-but-reported-active ports 6 and 7 and stale descriptions

Prepared an AI-assisted configuration review and an undeployed staging baseline: and generated a targeted relabel/enable command set.

Prepared an AI-assisted configuration review and an undeployed staging baseline: It also translated a device/port matrix and TLMMSTR reference into a ready-to-stage CERFLTSW1 baseline with VLANs 43

Prepared an AI-assisted configuration review and an undeployed staging baseline: 48

Prepared an AI-assisted configuration review and an undeployed staging baseline: 49

Prepared an AI-assisted configuration review and an undeployed staging baseline: 60

Prepared an AI-assisted configuration review and an undeployed staging baseline: and 999

Prepared an AI-assisted configuration review and an undeployed staging baseline: management address 10.62.49.40/24

Prepared an AI-assisted configuration review and an undeployed staging baseline: eight access-port definitions

Prepared an AI-assisted configuration review and an undeployed staging baseline: and two independent trunks without EtherChannel/LACP.

Prepared an AI-assisted configuration review and an undeployed staging baseline: No generated configuration is described as deployed

Prepared an AI-assisted configuration review and an undeployed staging baseline: authorized OT review

Prepared an AI-assisted configuration review and an undeployed staging baseline: cybersecurity checks

Prepared an AI-assisted configuration review and an undeployed staging baseline: backups

Prepared an AI-assisted configuration review and an undeployed staging baseline: change control

Prepared an AI-assisted configuration review and an undeployed staging baseline: rollback

Prepared an AI-assisted configuration review and an undeployed staging baseline: and post-change tests remain mandatory.

Actions, Methods & Controls

ACTIVITIES IN CONTEXT

Additional Technical Detail

Roles & contributions
  • Project Ownership

    Full lifecycle project ownership

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

  • IT Team

    Project Team Contribution

    Team Contribution

    IT participated in lab/live transition validation and the controls-network cutover interface.

  • Fiber and Electrical Contractors

    Supplier Participation

    Vendor Contribution

    Fiber/electrical contractors carried field-installation work within the phased implementation; procurement and equipment sources included equipment distributor, network equipment supplier, Insight and network equipment supplier.

Workstream context
Additional technical detail
Explore 1 detail record
  • OT change requirement

    For LAL-23, AI aligned physical observations with switch configuration, identified shutdown-but-reported-active ports 6 and 7 and stale descriptions, and generated a targeted relabel/enable command set. It also translated a device/port matrix and TLMMSTR reference into a ready-to-stage CERFLTSW1 baseline with VLANs 43, 48, 49, 60, and 999; management address 10.62.49.40/24; eight access-port definitions; and two independent trunks without EtherChannel/LACP. No generated configuration is described as deployed; authorized OT review, cybersecurity checks, backups, change control, rollback, and post-change tests remain mandatory.

All portfolio connections
All portfolio connections (20)
Project ownership and delivery context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Developed the fiber and managed-switch architecture, resilient power arrangements, configuration and rollback requirements, and cutover sequence. Network drawings, device labeling and validation connected the installation with operator and maintenance needs. The work included a 10 Gbps backbone and 13 UPS-backed resilience points.

Related analysis and application artifacts
Connected collections

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗