| Centrifuge Throughput Target | 40 GPM | Target Trial operating target | Applies to: Winery Centrifuge Trial Prep and Utility Coordination 40 GPM operating target |
| Outlet Clarity Target | 20 to 30 NTU | Target Trial target | Applies to: Winery Centrifuge Trial Prep and Utility Coordination 20–30 NTU outlet target |
| Brew 250 Outlet Turbidity | 36 to 40 NTU | Observation Trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination After temporary deaeration-nozzle correction — approximately 36–40 NTU observed after nozzle correction |
| Brew 250 Later Throughput | 40 GPM | Observation Later trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination After nozzle correction — Brew 250 subsequently operated at 40 GPM near the established baseline; distinct from the earlier 20 GPM supplier-comparison limitation. |
| Flow | 40 GPM | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded flow at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Inlet Turbidity | 482.9 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline inlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Outlet Turbidity | 17.3 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline outlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Laboratory Inlet Turbidity | 687 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded laboratory inlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Benchtop Inlet Turbidity | 661 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded desk benchtop inlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Laboratory Outlet Turbidity | 51.7 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded laboratory outlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Benchtop Outlet Turbidity | 46.6 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded desk benchtop outlet turbidity at 40 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Flow | 30 GPM | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded flow at 30 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Inlet Turbidity | 490.4 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline inlet turbidity at 30 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Outlet Turbidity | 8.3 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline outlet turbidity at 30 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Laboratory Outlet Turbidity | 44 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded laboratory outlet turbidity at 30 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Benchtop Outlet Turbidity | 39.7 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded desk benchtop outlet turbidity at 30 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Flow | 20 GPM | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded flow at 20 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Inlet Turbidity | 505.5 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline inlet turbidity at 20 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Inline Outlet Turbidity | 5.3 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded inline outlet turbidity at 20 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Laboratory Outlet Turbidity | 40.2 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded laboratory outlet turbidity at 20 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Benchtop Outlet Turbidity | 36.5 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Recorded desk benchtop outlet turbidity at 20 GPM; inline EBC and benchtop NTU remain separate instrument observations. |
| Pre-Nozzle Inline Outlet Turbidity | 52.2 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor nozzle-comparison report;66% is the reported reduction, distinct from bench NTU values. |
| Post-Nozzle Inline Outlet Turbidity | 17.3 EBC | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor nozzle-comparison report;66% is the reported reduction, distinct from bench NTU values. |
| Reported Outlet-Solids Reduction | 66 % | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor nozzle-comparison report;66% is the reported reduction, distinct from bench NTU values. |
| Comparison Flow | 40 GPM | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor nozzle-comparison report;66% is the reported reduction, distinct from bench NTU values. |
| Additional Benchtop Spin Duration | 10 min | Design Parameter Vendor benchtop comparison method | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor sample comparison at 40 GPM; supports its interpretation of residual turbidity, not a universal separation guarantee. |
| Outlet-Sample Turbidity Before Additional Spin | 46.6 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor sample comparison at 40 GPM; supports its interpretation of residual turbidity, not a universal separation guarantee. |
| Outlet-Sample Turbidity After Additional Spin | 38.2 NTU | Observation Vendor trial observation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Vendor sample comparison at 40 GPM; supports its interpretation of residual turbidity, not a universal separation guarantee. |
| Earlier Steady-State Turbidity Baseline | 15 to 20 NTU | Baseline Reported baseline | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Earlier reported baseline before recent fermentation changes. |
| Recent Fermentation Turbidity | 38 NTU | Observation Reported batch context | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Reported turbidity after fermentation changes such as extra yeast to restart stalled batches. |
| Different Batches Filtered | 2 batch | Scope or Inventory Quantity Trial context | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Only two materially different batches had been filtered in over a month, limiting trial comparability. |
| Laboratory Centrifuge Outlet Turbidity | 17 to 20 NTU | Observation Laboratory comparison | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Separate startup assessment; do not merge with later 36–40 NTU fermentation conditions. |
| Field Centrifuge Outlet Turbidity at 25 GPM | 21 to 28 NTU | Observation Field comparison | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Separate startup assessment; do not merge with later 36–40 NTU fermentation conditions. |
| Estimated Dissolved-Impurity Contribution | 10 to 12 NTU | Estimate Engineering interpretation | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Separate startup assessment; do not merge with later 36–40 NTU fermentation conditions. |
| Existing Acetator Feed Turbidity | < 5 NTU | Baseline Reported feed baseline | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Existing feed reported below 5 NTU. |
| Field Centrifuge Flow | 25 GPM | Observation Field comparison | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Flow for the separate 21–28 NTU field assessment. |
| Fermenter Volume | 26,000 gal | Scenario or Model Result Operating model | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Operating-window sizing calculation, not a completed-batch performance result. |
| Available Filtration Window | 17.5 h | Scenario or Model Result Operating model | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Operating-window sizing calculation, not a completed-batch performance result. |
| Modeled Filtration Flow | 25 GPM | Scenario or Model Result Operating model | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Operating-window sizing calculation, not a completed-batch performance result. |
| Calculated Window Capacity | 26,250 gal | Scenario or Model Result Operating model | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Operating-window sizing calculation, not a completed-batch performance result. |
| Minimum Comparison Flow Requirement | >= 25 GPM | Target Requirement | Applies to: Winery Centrifuge Trial Prep and Utility Coordination supplier comparison — Requested minimum throughput for the vendor comparison. |
| Higher-Turbidity Flow Alternative | 40 to 50 GPM | Target Operating alternative | Applies to: Winery Centrifuge Trial Prep and Utility Coordination supplier comparison — Flow alternative discussed with higher outlet turbidity. |
| Annual Design-Load Scenario | approximately 5,000,000 gal/year | Design Parameter Design basis | Applies to: Winery Centrifuge Trial Prep and Utility Coordination centrifuge sizing — Approximate annual throughput used in one supplier-sizing scenario. |
| Weekly Product-Load Scenario 1 | 40,000 gal/week | Design Parameter Design basis | Applies to: Winery Centrifuge Trial Prep and Utility Coordination centrifuge sizing — One of three separately listed weekly product loads in the sizing discussion. |
| Weekly Product-Load Scenario 2 | 40,000 gal/week | Design Parameter Design basis | Applies to: Winery Centrifuge Trial Prep and Utility Coordination centrifuge sizing — One of three separately listed weekly product loads in the sizing discussion. |
| Weekly Product-Load Scenario 3 | 9,000 gal/week | Design Parameter Design basis | Applies to: Winery Centrifuge Trial Prep and Utility Coordination centrifuge sizing — One of three separately listed weekly product loads in the sizing discussion. |
| FY 25 Production Planning Question | 8,600,000 gal/year | Unresolved Value Planning question | Applies to: Winery Centrifuge Trial Prep and Utility Coordination FY 25 discussion — Annual figure raised for confirmation in the later planning discussion. |
| Temporary Clarity-Focused Flow Alternative | 15 to 20 GPM | Target Operating alternative | Applies to: Winery Centrifuge Trial Prep and Utility Coordination acetator acclimation review — Lower flow considered while checking solids removal and acetator response. |
| Fermenter Manifold to Pass-Through Hose Length | 25 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Fermenter manifold to pass-through. |
| Pass-Through to Feed-Pump Inlet Hose Length | 15 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Pass-through to feed-pump inlet. |
| Feed Pump to Centrifuge Hose Length | 15 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Feed pump to centrifuge. |
| Product Outlet to Storage Pipe Hose Length | 10 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Product outlet to storage pipe. |
| Waste-Hose Length | 30 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Waste hose. |
| CIP Tank to Pump Hose Length | 20 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — CIP tank to pump. |
| Centrifuge to CIP-Tank Top Hose Length | 30 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Temporary trial hose schedule — Centrifuge to CIP-tank top. |
| CIP Tank Purchasing Alternative | 100 gal | Equipment Rating Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination site readiness — Tank purchase alternative if the existing larger poly tank was unavailable. |
| Engineering-Network Ethernet Route | 100 to 200 ft | Design Parameter Installation planning | Applies to: Winery Centrifuge Trial Prep and Utility Coordination engineering network — Approximate route to the QA-lab master switch. |
| Additional Operator-Training Request | approximately 1 day | Target Schedule request | Applies to: Winery Centrifuge Trial Prep and Utility Coordination Supplier startup planning — Requested extra training duration subject to pricing. |
| Solids Removal | 95 % | Observation Trial observation | Applies to: Centrifuge Trial Performance, Documentation, and Supplier Tradeoff Analysis Centrifuge supplier comparative trial — 95% solids removal at 40 GPM |
| Trial Throughput | 40 GPM | Observation Trial observation | Applies to: Centrifuge Trial Performance, Documentation, and Supplier Tradeoff Analysis Centrifuge supplier comparative trial — 95% solids removal at 40 GPM |
| Solids Removal | 83 % | Observation Trial observation | Applies to: Centrifuge Trial Performance, Documentation, and Supplier Tradeoff Analysis Centrifuge supplier comparative trial — 83% at 50 GPM |
| Trial Throughput | 50 GPM | Observation Trial observation | Applies to: Centrifuge Trial Performance, Documentation, and Supplier Tradeoff Analysis Centrifuge supplier comparative trial — 83% at 50 GPM |
| Oil-Change Procedure Duration | 10 min | Observation Vendor training record | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier startup, 2024-10-22 — Centrifuge supplier reported demonstrating the ten-minute oil-change process during operator training at the startup. |
| Flow | 30 GPM | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Initial Apple Wine startup — Vendor-reported initial apple wine startup: flow. |
| Outlet Backpressure | 150 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Initial Apple Wine startup — Vendor-reported initial apple wine startup: outlet backpressure. |
| Flow | 30 GPM | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — After inline-to-lab scaling — Vendor-reported after inline-to-lab scaling: flow. |
| Outlet Backpressure | 100 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — After inline-to-lab scaling — Vendor-reported after inline-to-lab scaling: outlet backpressure. |
| Outlet Turbidity | 17 NTU | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — After inline-to-lab scaling — Vendor-reported after inline-to-lab scaling: outlet turbidity. |
| Flow | 40 GPM | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Raised flow — Vendor-reported raised flow: flow. |
| Outlet Backpressure | 100 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Raised flow — Vendor-reported raised flow: outlet backpressure. |
| Outlet Turbidity | 20 NTU | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Raised flow — Vendor-reported raised flow: outlet turbidity. |
| Flow | 40 GPM | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Reduced outlet backpressure — Vendor-reported reduced outlet backpressure: flow. |
| Outlet Backpressure | 75 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Reduced outlet backpressure — Vendor-reported reduced outlet backpressure: outlet backpressure. |
| Outlet Turbidity | 20 NTU | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Reduced outlet backpressure — Vendor-reported reduced outlet backpressure: outlet turbidity. |
| Flow | 50 GPM | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Following-day repeated run — Vendor-reported following-day repeated run: flow. |
| Outlet Backpressure | 100 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Following-day repeated run — Vendor-reported following-day repeated run: outlet backpressure. |
| Outlet Turbidity | 23 NTU | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Following-day repeated run — Vendor-reported following-day repeated run: outlet turbidity. |
| Stable Production Duration | approximately 5 h | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor reported approximately five hours without production issues at the stated settings after the air adjustment. |
| Additional Air-Pressure Adjustment | 5 psi | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor increased supply air another 5 psi after a low-pressure alarm. |
| Solids Discharge Interval | 4 to 5 min | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor-reported discharge interval at 50 GPM; solids packing and post-rinse needs varied with flow. |
| Solids Discharge Interval | 12 to 13 min | Observation Vendor trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor-reported discharge interval at 40 GPM; solids packing and post-rinse needs varied with flow. |
| Automatic Recipe Flow | 50 GPM | Operating Control Configured trial recipe | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor-developed automatic recipe; 10 GPM was a slow overnight option with occasional checks recommended. |
| Automatic Recipe Flow | 40 GPM | Operating Control Configured trial recipe | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor-developed automatic recipe; 10 GPM was a slow overnight option with occasional checks recommended. |
| Automatic Recipe Flow | 10 GPM | Operating Control Configured trial recipe | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier trial, 22–23 October 2024 — Vendor-developed automatic recipe; 10 GPM was a slow overnight option with occasional checks recommended. |
| Operator-Reported Flow | 40 GPM | Observation Operator trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier operator report, 25 October 2024 — Operator report of the stated run; no reported issues during this 5,500 gallon observation. |
| Operator-Reported Outlet Turbidity | 21 NTU | Observation Operator trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier operator report, 25 October 2024 — Operator report of the stated run; no reported issues during this 5,500 gallon observation. |
| Operator-Reported Processed Volume | 5,500 gal | Observation Operator trial observation | Applies to: Centrifuge filtration recovery and equipment-relocation evaluation Centrifuge supplier operator report, 25 October 2024 — Operator report of the stated run; no reported issues during this 5,500 gallon observation. |