Food and Beverage Manufacturer
Boiler System + Plant Steam & Condensate Optimization
Owned the full project lifecycle, from capital planning through commissioning and post-startup support. Steam capacity alone did not determine process performance.
APOLLO AUTOMATIONJAMES WARREN · ENGINEERING & PROJECT LEADERSHIPCASE-073 · Engineering case
Led the boiler, feedwater, condensate and boiler-room modernization as an integrated thermal-utility project.

The boiler project required correcting generation capacity, heat recovery, feedwater quality, condensate return, steam routing, PRV/control instability, room construction, permitting, and commissioning as one system.
Coordination scope: 350 HP, 2-pass dryback firetube boiler; economizer; LMV51 BMS; CM burner; natural gas piping; flue stack; roof penetration flashing; economizer piping; insulation strategy; 350-gal stainless feedwater tank skid; dual CR5-18K pumps rated 35 GPM at 445 ft TDH, 7.5 hp; Model 10SS deaerator; level control; steam injection heater; chemical quills; solenoid makeup valve with bypass; NEMA 12 enclosure; twin FRP 160,000 grain softeners; reused chemical pumps/tanks with flow-based chemical dosing; 150 ft condensate return pipe with 36 in drop; steam trap routing corrections; 3 in steam isolation valves for disused mains; 22 ft x 28 ft x 20 ft CMU boiler room; 10 ft x 10 ft x 20 ft equipment room; 8 in 4500 PSI slab; roll-up door; R29 roof; city permitting; electrical feeds; BMS commissioning; I/O checkout; instrumentation calibration; operator training; P&IDs, PFD, instrument list, control narrative, electrical power plan, 3D scan, 29-30 week APO schedule, and A207360 schedule.
Improved steam reliability, condensate management, and boiler infrastructure; energy-performance figures retain their reported, projected, or modeled bases.
Workstream Portfolio Rollup
16,297,000 USD
Steam and Boiler System Modernization
Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.
| Measure | Value | Type & meaning | Attribution & operating context |
|---|---|---|---|
| Rental Boiler Cost Avoidance | 15,000 USD/month | Estimate Projected rental avoidance | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Boiler replacement business case — projected $15K/month rental avoidance |
| Annual Energy Savings | > 11,000 USD/year | Historical/Reference Value Reported annual energy benefit | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Annual energy-benefit figure reported in the boiler project narrative. It is retained separately from the 1.135 MMBtu/h savings commitment, 0.5 MMBtu/h modeled benefit and projected rental avoidance. |
| Annual Fuel Reduction | 10 to 15 % | Historical/Reference Value Reported annual fuel-reduction range | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Reported 10–15% annual fuel-reduction reference in the boiler project narrative, alongside separate modeled savings and commitment values. |
| Boiler Efficiency | 79.8 % | Baseline Before heat recovery | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Baseline — Efficiency baseline before the recorded heat-recovery improvement. |
| Boiler Efficiency | 82.8 % | Historical/Reference Value Reported post-change reference | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Heat-recovery comparison — Reported 82.8% post-change efficiency in the heat-recovery comparison, paired with the 79.8% baseline. |
| Fuel-Savings Commitment | 1.135 MMBtu/h | Target Commitment | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Recorded 1.135 MMBtu/h fuel-savings commitment; distinct from the 0.5 MMBtu/h modeled value. |
| Modeled Fuel Savings | 0.5 MMBtu/h | Scenario or Model Result Modeled benefit | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Modeled 0.5 MMBtu/h fuel savings; not interchangeable with the separate 1.135 MMBtu/h commitment. |
| Flue Gas Temperature | 398 degF | Baseline Before heat recovery | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Baseline — Flue gas temperature before heat recovery. |
| Flue Gas Temperature | 285 degF | Historical/Reference Value Reported post-change reference | Applies to: Boiler System Overhaul and Steam / Condensate Optimization Heat-recovery comparison — Reported 285 degF post-change flue-gas temperature in the heat-recovery comparison, paired with the 398 degF baseline. |
Improved steam capacity, reduced rental exposure, corrected condensate failures, and strengthened BMS/control readiness; fuel-efficiency improvement remains a reported performance reference.
Coordinated 350 HP 2-pass dryback firetube boiler; economizer; LMV51 BMS; CM burner; natural gas piping; flue stack; roof penetration flashing; economizer piping; insulation strategy; 350-gal stainless feedwater tank skid; dual CR5-18K pumps rated 35 GPM at 445 ft TDH, 7.5 hp; Model 10SS deaerator; level-control system; steam injection heater; chemical quills; solenoid makeup valve with bypass; NEMA 12 enclosure; twin FRP 160,000 grain softeners; reused chemical pumps/tanks with flow-based chemical dosing; 150 ft condensate return pipe with 36 in drop; steam trap routing corrections; 3 in steam isolation valves for disused mains; 22 ft x 28 ft x 20 ft CMU boiler room; 10 ft x 10 ft x 20 ft equipment room; 8 in 4500 PSI slab; roll-up door; R29 roof; city permitting; electrical feeds; BMS commissioning; I/O checkout; instrumentation calibration; operator training; P&IDs, PFD, instrument list, control narrative, electrical power plan, 3D scan, 29-30 week APO schedule, and A207360 schedule.
Improved thermal utility reliability, measured by $1.45M total capital, $1.2M boiler-room/equipment layer, projected $15K/month rental boiler elimination, a reported 10-15% annual fuel-reduction reference, and 1.135 MMBtu/hrfuel-savings commitment, by coordinating boiler, economizer, feedwater, deaerator, condensate, controls, building, and commissioning scope.
boiler-room/equipment layer; projected $15K/month rental avoidance; reported 10-15% annual fuel-reduction reference; 1.135 MMBtu/hr fuel-savings commitment; 0.5 MMBtu/hr modeled fuel savings; reported flue-gas values of 398 F and 285 F; reported efficiency values of 79.8% and 82.8%; reported >$11K/year energy-savings reference.
Led boiler-replacement engineering and coordinated the economizer, BMS, feedwater/deaerator skid, water softening, condensate rebuild, steam diagnostics, boiler-room construction, permits, controls testing and commissioning.
ACTIVITIES IN CONTEXT

TSK-000158 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000159 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000160 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000161 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000162 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000163 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000164 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000165 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000166 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000167 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000168 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000169 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000170 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000171 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000172 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000173 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000174 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000175 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000176 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000177 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000178 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000179 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000180 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000181 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000182 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000183 · Technical scope
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000184 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000185 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000186 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000187 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000188 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-000189 · Method
Boiler System Overhaul and Steam / Condensate Optimization

TSK-001063 · Action
Boiler System Overhaul and Steam / Condensate Optimization

TSK-001064 · Engineering scope
Boiler System Overhaul and Steam / Condensate Optimization
Full lifecycle project ownership
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.
Coordinated boiler-room equipment, electrical and controls interfaces with steam-manifold and pressure-reduction improvements. Condensate recovery, control checkout and operating readiness were part of the same system scope. The work increased available steam capacity by about 25 percent and stabilized jacket pressure.