CASE-111 · Engineering case

Fiberoptic OT Network Phase 1 and Phase 2, Configuration and Cutover Execution

Transitioned engineering controls from shared IT infrastructure to a dedicated OT fiber backbone with staged physical installation, switch programming, IP migration, and live validation.

Conceptual engineering visualization: Fiberoptic OT Network Phase 1 and Phase 2, Configuration and Cutover Execution
Conceptual engineering visualization · AI generated

Why the Work Mattered

Purpose and Operating Need

The project required more than fiber installation; it required comparing the existing managed network standard with new OT architecture, switch-stack uplinks, VLAN segmentation, IP migration, cable moves, and validation with limited remote IT support.

Engineering Approach

Engineering Approach

Methods and technical scope: distribution switches distribution switches, managed access switches managed access switches, dual SFP uplinks, LACP / Port-Channel planning, VLAN segmentation, IEEE 802.1Q tagging, inter-VLAN SVI validation, redundant star topology, lab programming, live IP migration, NEMA 4X stainless IDF enclosures, armored OM3 50/125 fiber, UPS-backed switches, and IT handoff testing.

Outcome & Engineering Context

Outcome and Context

Improved OT reliability, security, bandwidth, and migration control within the implemented portions of the phased network; remaining commissioning was recorded separately.

Workstream Results & Impact

Workstream Portfolio Rollup

4,942,000 USD

OT Network and Controls Transformation

Recorded workstream portfolio reference. This is the workstream-level value and is not a project expenditure or a new total of reassigned projects.

Measures & Operating Detail

MeasureValueType & meaningAttribution & operating context
East-West OT Backbone Data Rate10 GbpsEquipment Rating
Network architecture capacity

Applies to: Fiberoptic OT Network Phase 1 and Phase 2, Configuration and Cutover Execution

10 Gbps backbone

Installation Readiness Before Equipment Receipt80 %Observation
Readiness snapshot

Applies to: Fiberoptic OT Network Phase 1 and Phase 2, Configuration and Cutover Execution

Before final equipment receipt — Installation readiness before equipment receipt

Engineering scope and design basis

Improved process-network security, latency, bandwidth, failover, and power-sag resilience within the implemented portions of the phased OT work; the associated execution record retains 20% future commissioning.

Used distribution switches distribution switches, managed access switches managed access switches, dual SFP uplinks, LACP / Port-Channel planning, VLAN segmentation, IEEE 802.1Q tagging, inter-VLAN SVI validation, redundant star topology, lab programming, live IP migration, NEMA 4X stainless IDF enclosures, armored OM3 50/125 fiber, UPS-backed switches, and IT handoff testing.

Improved OT network reliability and migration control, measured by Phase 1, Phase 2, 8 Phase 1 fiber enclosures, 5 additional Phase 2 network zones, 13 UPS units, 10 Gbps east-west backbone, by coordinating fiber installation, switch programming, IP migration, contractor qualification, and live validation.

Phase 1; Phase 2; 8 Phase 1 enclosures; 5 Phase 2 added zones; 13 UPS units; 10 Gbps backbone.

Actions, Methods & Controls

ACTIVITIES IN CONTEXT

Additional Technical Detail

Roles & contributions
  • Project Ownership

    Full lifecycle project ownership

    Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

  • IT Team

    Project Team Contribution

    Team Contribution

    IT participated in lab/live transition validation and the controls-network cutover interface.

  • Fiber and Electrical Contractors

    Supplier Participation

    Vendor Contribution

    Fiber/electrical contractors carried field-installation work within the phased implementation; procurement and equipment sources included equipment distributor, network equipment supplier, Insight and network equipment supplier.

Workstream context
All portfolio connections
All portfolio connections (22)
Project ownership and delivery context

Owned the full project lifecycle: capital planning and prioritization, need definition, feasibility and scope development, engineering and AFE justification, procurement and vendor coordination, construction sequencing and field oversight, commissioning, turnover, and post-startup support. Connected operating requirements with technical scope, funding decisions, execution readiness, and the needs of operations and maintenance.

Developed the fiber and managed-switch architecture, resilient power arrangements, configuration and rollback requirements, and cutover sequence. Network drawings, device labeling and validation connected the installation with operator and maintenance needs. The work included a 10 Gbps backbone and 13 UPS-backed resilience points.

Related methods and applications
Related analysis and application artifacts
Connected collections

WHAT COMES NEXT

Complex Challenge?
Let’s Work Through It.

Engineering leadership, capital projects, and independent consulting.

Start a conversation ↗